Project Management
Hello.
Here is a summary of all you need to know towards CompTIA or PMP project management examinations.
Here is a summary of all you need to know towards CompTIA or PMP project management examinations.
1.
Initiating
a project
Summary
A project is a temporary endeavor that produces a unique
product, service, or result. It has definitive start and finish dates.
Project management is the application of tools and techniques
to organize the project activities to successfully meet the project goals.
A project manager is responsible for project integration
and applying the tools and techniques of project management to bring about a
successful conclusion to the project.
Organizational structures impact how projects are managed
and staffed. The primary structures are functional, matrix, and project-based.
The traditional departmental hierarchy in a functional organization provides
the project manager with the least authority. The other end of the spectrum is
the project - based organization, where resources are organized around
projects; in these types of organizations, the project manager has the greatest
level of authority to take action and make decisions regarding the project. The
matrix organization is a middle ground between the functional organization and
the project - based organization.
Project selection techniques involve the use of decision
models, such as a cost - benefit analysis and expert judgment, to allocate
limited resources to the most critical projects.
Project managers are individuals charged with overseeing
every aspect of a given project from start to finish. A project manager needs
not only technical knowledge of the product or service being produced by the
project, but also a wide range of general management skills.
Key general management skills include leadership,
communication, problem solving, negotiation, organization, and time management.
Exam Nuggets
Be able to define a project. A project brings about a unique
product, service, or result and has definite beginning and ending dates.
Be able to identify the difference between a project and
ongoing operations. A
project is a temporary endeavor to create a unique product or service.
Operational work is ongoing and repetitive.
Be able to understand the three types of organizational
structures. The
three types of organizational structures are functional, matrix, and project -
based structures. Matrix organizations may be structured as a strong matrix,
weak matrix, or balanced matrix organization.
Be able to define the role of a project manager. A project manager’s core function
is project integration. A project manager leads the project team and oversees
all the work required to complete the project goals to the satisfaction of the
stakeholders.
Be able to identify the most common project selection
methods. The most
common project selection methods are benefit measurement methods such as cost -
benefit analysis, scoring models, payback period, and economic models (which
include discounted cash flows, NPV, and IRR), as well as expert judgment.
Understand what skills are needed to manage a project
beyond technical knowledge of the product. Key general management skills include leadership,
communication, problem solving, negotiation, organization, and time management
2. Project
Process Groups and the Project Charter
Summary
Collectively, project management consists of five process
groups: Initiating, Planning, Executing, Monitoring and Controlling, and
Closing. Each of these process groups consists of individual processes that
each have inputs, tools and techniques, and outputs. The primary output of the
Initiating process group is the project charter.
Initiation is the formal authorization for the project to
begin. It starts with a project request that outlines the high - level
requirements, or the product description. There are three types of
requirements: functional, business, and technical.
A Project stakeholder is anyone who has a vested interest
in the outcomes of the project. Some project stakeholders you will likely
encounter include the project sponsor, team members, functional managers,
customers (both internal and external), and end users.
A project sponsor is an executive in the organization who
has the authority to assign budget and resources to the project. Project
sponsors serve as final decision makers on the project and sign and approve the
project charter.
The output from the Initiating process is the project
charter. This document becomes the basis for more-detailed project planning. It
should contain the project description, project approach, stakeholders, goals
and objectives, problem statement, high - level deliverables, milestones, costs,
assumptions, constraints, and risk.
Exam nuggets
Be able to define the Initiating process. Initiation authorizes the project
to begin.
Understand the three categories of requirements. Functional requirements define how
the user will interact with the system. Business requirements are the big
picture of what the business wants from the system. Technical requirements
define what the system does to perform the functional requirements.
Be able to define a project sponsor and the stakeholders’
common to most projects. A
project sponsor is an executive in the organization who has the authority to
allocate funds and resources to the project.
A stakeholder is an organization or someone who has a
vested interest in the project and has something to gain or lose from the
project. Stakeholders include the sponsor, project manager, project team
members, functional managers, customer, end users, and others with an interest
in the project.
Be able to describe a project charter and list the key
components. A
project charter provides formal approval for the project to begin and
authorizes the project manager to apply resources to the project. The key
components are the problem statement, deliverables, milestones, costs,
assumptions, constraints, risks, stakeholders, and project description.
3.
Planning a Project
Summary
Scope planning uses the output of the Initiating process,
the project charter, to create the scope statement and the scope management
plan. The scope management plan documents the process you’ll use to prepare the
project scope statement and WBS, a definition of how the deliverables will be
verified, and a description of the process for controlling scope change
requests.
The project scope statement is the basis for many of the
planning processes and future change decisions. It is also the basis for
setting the boundaries of the project with the customer and stakeholders. A
scope statement includes the product description, key deliverables, success and
acceptance criteria, key performance indicators, exclusions, time and cost
estimates, assumptions, and constraints.
The work breakdown structure (WBS) is created by taking the
major deliverables from the scope statement and decomposing them into smaller,
more manageable components. The breakdown continues through multiple levels
until the components can be estimated and resourced. The lowest level of
decomposition is the work package. The WBS includes all the work required to
complete the project. Any deliverable or work not listed on the
WBS is assumed to be excluded from the project. The WBS is
a critical component of project planning. A WBS is the basis for time
estimates, cost estimates, and resource assignments.
The WBS dictionary should list every deliverable and each
of their components contained in the WBS. It should include a description of
the component, code of account identifiers, responsible party, estimates,
criteria for acceptance, and any other information that helps clarify the
deliverables and work components.
Exam nuggets
Describe the purpose of a scope management plan. A scope management plan documents the
procedures for preparing the project scope statement and WBS, defines how the deliverables
will be verified, and describes the process for controlling scope change requests.
Understand the purpose of the scope statement. The scope statement is the basis of
the agreement between the project and the customer concerning what comprises
the work of the project. It defines the deliverables and success criteria that
will meet those objectives.
Be able to list the components of a scope statement. A scope statement includes a
product description, key deliverables, success and acceptance criteria, key
performance indicators, exclusions, assumptions, and constraints.
Know how to define and create a work breakdown structure
(WBS). The WBS is
a deliverable - oriented hierarchy that describes the work required to complete
the project. The WBS is a multilevel tree diagram that starts with the project,
includes the major deliverables, and decomposes the major deliverables into
smaller units of work to the point where time and cost estimates can be
provided and resources assigned.
Understand the levels in a WBS. The highest level of the WBS is the
project name. The major deliverables, project phases, or subprojects make up
the next level. The number of levels in a WBS will vary by project; however,
the lowest level of the WBS is a work package.
Describe a WBS dictionary. The WBS dictionary describes each
of the deliverables and their components and includes a code of accounts
identifier, estimates, resources, criteria for acceptance, and any other
information that helps clarify the deliverables.
4. Schedule
Planning
Summary
Many steps are involved in schedule planning. Activity Definition
takes the work packages from your WBS and breaks them down into assignable
tasks. Activity Sequencing looks at dependencies between tasks. These dependencies
can be mandatory, discretionary, or external. A dependent task is either a
successor or a predecessor of a linked task. There are four types of logical
relationships: finish-to-start, start-to-start, start-to-finish, and
finish-to-finish. A network diagram is a pictorial representation of the
task-dependency (logical) relationships.
Activity Duration estimating is obtained using analogous
(also called top - down) estimating, parametric estimating, expert judgment,
three - point estimates, and PERT.
The most complex schedule planning process is Schedule
Development. The critical path method (CPM) creates a schedule by calculating
forward and backward passes through the network diagram and then determining float.
Float is the difference between the early and late start
dates and the early and late finish dates. The critical path is the longest
full path on the project.
Duration compression is the technique used to shorten a
project schedule to meet a mandated completion date. Crashing shortens task
duration by adding more resources to the project. Fast tracking is where two tasks
are started in parallel that were previously scheduled to start sequentially.
A project schedule may be displayed as a milestone chart.
Milestones mark major project events such as the completion of a key
deliverable or project phase. Gantt charts are a common method to display
schedule data as well. The completed, approved project schedule becomes the
baseline for tracking and reporting project progress.
Exam nuggets
Describe the Activity Sequencing process. Activity Sequencing is the process
of identifying dependency relationships between the project activities and scheduling
activities in the proper order.
Name the two major relationships between dependent tasks. A predecessor is a task that exists
on a path with another task and occurs before the task in question. A successor
is a task that exists on a common path with another task and occurs after the
task in question.
Name the four types of logical relationships. The four types of logical
relationships are finish-to-start, start-to-start, start-to-finish, and finish-to-finish.
Know and understand the five most commonly used techniques
to estimate activity duration. Expert judgment relies on the knowledge of someone familiar
with the tasks. Analogous or top - down estimating bases the estimate on
similar activities from a previous project. Parametric estimates are
quantitatively based estimates that typically calculate the rate times
quantity. Three - point estimates use the most likely, optimistic, and
pessimistic estimates to determine an average estimate. PERT uses the same
estimates as the three – point estimating technique, but it calculates an
expected value or weighted average estimate.
Define the purpose of CPM. CPM calculates the longest path in
the project. This path controls the finish date of the project. Any delay to a
critical path task will delay the completion date of the project.
Explain a network diagram. A network diagram is used in
Activity Sequencing to depict project activities and the interrelationships and
dependencies among these activities.
Name the two most common ways project schedules are
displayed. Project
schedules are typically displayed as milestone charts or Gantt charts; a Gantt
chart is a type of bar chart.
5. Communication,
Human Resources & Quality Plan
Summary
Most project managers spend the majority of their project
management time in the act of communicating. Communication is performed using
the sender - message – receiver model. Communications Planning is a process
where you determine who needs what types of communication, when, and in what
format, and how that communication will be disseminated. The network
communication model shows the lines of communication that exist between any
number of project participants.
Resource Planning involves determining all the materials,
goods, equipment, and human resources you’ll need to perform the work of the
project. You can depict the roles and responsibilities of human resources
graphically in a RAM or a RACI chart.
Human Resource Planning identifies the specific resources
that will be assigned to your project as well as how and when they will join
the project team and be returned to their functional department. You’ll
document the resources needed in the human resource management plan. Be aware
of constraints that may impact the human resource management plan, such as
labor union agreements, organizational structure, and economic conditions.
Staff acquisition is where you choose the team members (or
organizations) who will work on the project. You should be prepared to negotiate
with functional managers for resources and also be prepared to interview
potential team members to determine experience levels, skill, and overall fit
on the team.
Procurement planning is performed when goods or services
for the project will be provided outside the organization. Procurement planning
involves a make - or - buy analysis, SOW preparation, vendor solicitation, and
vendor selection criteria. The typical solicitation vehicles for contracting
include an RFQ, RFP, and RFI or IFB.
Exam nuggets
Describe the importance of Communications Planning. Communications Planning is the key
to project success. It involves determining who needs information, when, and in
what format, and the frequency of the communication.
Describe Resource Planning. Resource Planning determines what
resources are needed for the project, including human, equipment, and material.
Describe a RAM. A RAM is a resource assignment matrix that shows the WBS
identifier, the type of resource required, and the number of resources for each
skill set. A RACI chart is a type of RAM that describes the resources and their
level of responsibility, including responsible, accountable, consult, or
inform.
Describe the two components of Human Resources Planning. The two components are organizational
planning and staff acquisition.
Be able to describe make - or - buy analysis. Make - or - buy analysis is
performed in order to determine the cost-effectiveness of either making or
buying the goods and services you need for the project.
Be able to name the types of contracts. The contract types include fixed-price,
cost- reimbursable, and time and materials.
6. Defining
the Cost, Quality, and Risk Plans
Summary
The Cost Estimating process is performed after the
resources for the project have been determined. You can use several techniques
to create project estimates.
Ø Analogous or top - down estimates
use expert judgment and historical data to provide a high - level estimate for
the entire project, a phase of the project, or a deliverable.
Ø Parametric estimating uses a mathematical
model to create the estimates and, in its simplest form, multiplies the
duration of the project task by the resource rate to determine an estimate.
Ø The bottom - up method creates the
project estimate by adding up the individual estimates from each work package.
Cost estimates are used to make up the project
budget. The project budget is established by using the organization’s chart of
accounts and then documenting work effort, duration, equipment and material
costs, and any other costs that may be incurred during the course of the
project.
The cost baseline
is the total approved expected cost for the project and is used for forecasting
and tracking expenditures throughout the project.
Quality Planning identifies the quality standards
that are applicable to the project and determines how the project will meet
those standards. Some of the most common tools used in Quality Planning include
cost - benefit analysis, benchmarking, flowcharting, and cost of quality.
Cost of quality is the total cost of all the work
required to assure the project meets the quality standards. There are three
types of quality costs: prevention, appraisal, and failure costs.
Risk Planning involves identifying potential risk events
that could occur during the project, determining their probability of
occurrence, and determining their impact to the project.
Probability is always expressed as a number between 0.0 and
1.0. Risk response plans should be developed for those risks that have a high probability
of occurrence, have a significant impact to the project if they occur, or have
an overall risk score that is high.
Risks must be analysed, qualitatively and quantitatively.
Qualitative risk analysis involves multiplying the probability that a risk will
occur by the impact when it occurs to create risk exposure. Quantitative risk analysis involves ranking of risks
and finding their cost and time contingencies.
The final project management plan consists of all the
documents created during the planning phase of the project. It’s good practice
to obtain sign - off on the project plan from the sponsor and key stakeholders
before proceeding. Once approval is obtained, the project management plan
becomes the baseline for the project.
Exam nuggets
Know the difference between analogous, parametric, and
bottom - up estimating techniques. Analogous, or top - down, estimates use expert judgment and
historical data to provide a high - level estimate for the entire project, a
phase of the project, or a deliverable. Parametric estimates use a mathematical
model to create the estimates. The bottom - up method starts at the lowest
level of the WBS and calculates the cost of each item within the work packages
to obtain a total cost for the project or deliverable.
Name the two discretionary funding allocations a project
may receive. The
two types of discretionary funding are a contingency reserve and a management
reserve. Contingency reserves are monies set aside to cover the cost of
possible adverse events. Management reserves are set aside by upper management
and are used to cover future situations that can’t be predicted during project
planning.
Explain the purpose of a cost baseline. The cost baseline is the total
approved, expected cost for the project. It’s used in the Executing and
Monitoring and Controlling processes to monitor the performance of the project
budget throughout the project.
Name the Quality Planning tools and techniques. The Quality Planning tools and techniques
are cost - benefit analysis, benchmarking, flowcharting, and cost of quality.
Name the types of costs associated with the cost of
quality. The types
of costs associated with the cost of quality are prevention costs, appraisal
costs, and failure costs. Failure costs include both internal and external
failure costs.
Explain the three processes used to develop a risk
management plan. Risk
Identification is the process of identifying and documenting the potential
risk events that may occur on the project. Risk analysis evaluates the severity
of the impact to the project and the probability that the risk will actually
occur. Risk response planning is the process of reviewing the list of potential
risks impacting the project to determine what, if any, action should be taken
and then documenting it in a response plan.
Name the negative risk response strategies. The negative risk response
strategies are avoid, transfer, mitigate, and accept.
Name the positive risk response strategies. The positive risk response
strategies are exploit, share, and enhance.
7. Processing
Change Requests
Summary
As is peculiar in all aspects of existence, things change.
Changes come about for many reasons and may take the form of corrective
actions, preventive actions, and defect repairs.
An integrated change
control system manages change requests, determines the global impacts of a
change, and updates all impacted portions of the project plan when a change is
made. Typically, a change control board is established to review and either
approve, deny, or delay change requests.
Scope Control involves reviewing and analyzing
requests for scope changes, and updating the scope baseline documents if a
scope change occurs. The scope baseline consists of the scope statement, WBS,
and WBS dictionary.
Scope Verification is the process of formally
accepting the deliverables of the project and obtaining sign - off from the
stakeholders that they’re complete and acceptable.
Schedule Control involves determining the status of
the project schedule, determining whether changes have occurred or should
occur, and influencing and managing schedule changes. Particular emphasis
should be placed on monitoring critical path tasks. Schedule updates may be
required as a result of a schedule change. Schedule compression techniques
(fast-tracking and crashing) can be used to help manage schedule changes.
Risk Monitoring and Control is when the risk response plans
identified during planning are implemented if needed. Other activities that
occur in this process include identifying and prioritizing new risks,
implementing contingency plans based on a trigger event, and evaluating the
effectiveness of response plans.
Reporting Performance is the process that involves
collecting information regarding project progress and project accomplishments
and reporting it to the stakeholders. Any project element that goes outside
predefined limits requires action on the part of the stakeholder team. Trade -
offs between quality, scope, schedule, and cost are presented by the project
manager.
Cancellation of the project is also an action
for consideration if the project is no longer viable.
Exam nuggets
Name and describe the three types of change requests. Corrective actions bring the work
of the project into alignment with the project plan, preventive actions are
implemented to help reduce the probability of a negative risk event, and defect
repairs correct or replace components that are substandard or malfunctioning.
Describe the possible impacts to check for when evaluating
a major change to the project scope. A major change to the project scope may impact the critical
path, schedule end date, budget, and resources, as well as introduce new risks.
Describe the elements of a change management process. The elements of a change management
process include change request forms, a change request log, analysis of
changes, the CCB, coordination and communication with stakeholders, and
updating the affected project planning documents.
Explain the purpose of a CCB. The change control board reviews,
approves, denies, or delays change requests.
Describe the purpose for the Scope Control process. Scope Control involves monitoring
the status of the project scope, monitoring changes to the project scope, and
monitoring work results to ensure that they match expected outcomes.
Describe the purpose for the Scope Verification process. Scope Verification involves formally
accepting completed deliverables and obtaining sign - off from the stakeholders
indicating the deliverables are satisfactory and meet the stakeholders’
expectations.
Describe the purpose for the Schedule Control process. Schedule Control involves determining
the status of the project schedule, determining whether changes have occurred
or should occur, and influencing and managing schedule changes.
Describe the Risk Monitoring and Control Process. Risk Monitoring and Control is the process
of implementing the risk response plan, tracking and monitoring identified
risks, and identifying and responding to new risks as they occur.
8. Executing
the Project
Summary
Project execution is an exciting time because you finally
get to see results of the hard work from the Initiating and Planning processes.
But just because you are executing against a well - defined plan does not mean
that you can sit back and watch the project pieces fall into place. You have a
lot of work to do in this phase, including assembling and motivating the project
team, holding the kickoff meeting, and determining the organizational oversight
needed for the project.
Staffing issues may arise with the functional managers who
provided you with resources for the project. You should attempt to resolve
these issues with the functional manager directly, but if a compromise can’t be
reached, escalation to the sponsor may be required.
Successful team development includes ongoing team building
and management, training, and a meaningful rewards and recognition system. It’s
also a time to build and establish an open, trusting environment and to
encourage the free exchange of ideas.
As the work on the project progresses, you need to collect
data from team members regarding their progress on the project and prepare
status reports for the sponsor and stakeholders. It’s always important to
understand any rules, regulations, or internal processes that you should adhere
to when executing the work of the project.
Exam nuggets
Name some of the common causes of conflict. Common causes are competing
resource demands, expert judgment, and varying work styles.
Name the conflict - resolution techniques. The techniques are smoothing,
forcing, compromise, confronting, avoiding, and negotiating.
Name the conflict - resolution technique most often used by
project managers. This
is confronting, also known as problem solving. This technique involves
discovering the facts regarding the issue and letting the facts help define the
solution.
State the five stages of team development. They are forming, storming,
norming, performing, and adjourning.
Understand the various means to recognize or reward team
members. Team member
contributions can be recognized with monetary rewards or prizes, a mention in
the formal project review or status meeting, a letter to executive management,
a thank - you, or a team celebration.
State the purpose of a project kickoff meeting. The project kickoff meeting is a
way to formally introduce all project team members, to review the goals and the
deliverables for the project, to discuss roles and responsibilities, and to
review stakeholder expectations.
Explain the importance of organizational governance. Organizational governance recognizes
the importance of regulations, laws, and other standards that may impact the
project. This also involves internal processes, version control, and
checkin/checkout processes.
9. Controlling
the Project
Summary
Quality Control is the process of reviewing
project results and determining whether they comply with the standards
documented in the quality management plan and making any appropriate changes to
remove the causes of unacceptable quality when the standards are not met. Quality
Control is performed throughout the life of the project. You can use several
tools and techniques to perform Quality Control, including inspection,
prevention, histograms, Pareto diagrams, control charts, statistical sampling,
flowcharting, trend analysis, run charts, and Ishikawa diagrams.
Quality Control concerns identifying variances in
the process or results. There are three common causes of variance: random
variances, known or predictable variances, and variances that are always
present in the system.
Cost Control involves managing changes to the
project cost baseline. It’s also concerned with monitoring project budgets to
prevent unauthorized or incorrect costs from getting included in the cost
baseline.
Earned value measurement is a tool and technique that
measures the value of the work completed to date by comparing what you’ve
received or produced to what you’ve spent as of the measurement date by using
measurements such as CV, SV, CPI, SPI, ETC, and EAC.
Managing Stakeholder Expectations involves making sure certain
communication needs and expectations of the stakeholders are met, managing any
issues stakeholders might raise that could become future issues, and resolving
previously identified issues. One of the ways to manage expectations is to
manage the information distribution process.
The Distribute Information process is concerned with making certain
project information available to stakeholders at the right time and in the
appropriate format. Distribute Information is performed throughout the life of
the project.
Managing team members involves being aware of barriers and
differences that may impact communication and the productivity of the team,
including different time zones, communication and language barriers, cultural
differences, technology barriers, and hierarchical barriers.
Earned Value Measurement
EVM looks at schedule, cost, and scope project measurements
together and compares them to the actual work completed to date. It is the most
often used performance measurement method. EVM is performed on the work
packages and the control accounts of the WBS. To perform the EVM calculations,
you need to first gather these three measurements: planned value, actual cost,
and earned value.
Planned value: The planned value (PV) is the cost of work that has
been authorized and budgeted for a schedule activity or WBS component during a
given time period or phase. These budgets are established during the Planning
processes. PV is also known as the budgeted
cost of work scheduled (BCWS).
Actual cost: Actual cost (AC) is the actual cost of completing the work component in a given
time period. Actual costs might include direct and indirect costs but must
correspond to what was budgeted for the activity. If the budgeted amount did
not include indirect costs, do not include them here. Later you’ll see how to
compare this to PV to come up with variance calculation results. AC is also
known as the actual cost of work
performed (ACWP).
Earned value Earned value (EV) is the value of the work completed to date as it compares to
the budgeted amount (PV) for the work component. EV is typically expressed as a
percentage of the work completed compared to the budget. For example, if our
budgeted amount is ₦1,000 and we have completed 30 percent of the work so far,
our EV is ₦300. Therefore, EV cannot exceed the PV budget for the activity. EV
is also known as the budgeted cost of
work performed (BCWP).
PV, AC, and EV all include a
cost component. When costs are displayed graphically, they form an S curve. The
reason for this is that at the beginning of the project, spending is minimal;
then it picks up once the work of the project is underway, and it tapers off at
the end of the project as the work wraps up. Since earned value measurements
include a cost component, they are also displayed in an S curve.
Cost Variance: Cost variance is one of the most
popular EVM variances that project managers use. It tells you whether your
costs are higher than budgeted (with a resulting negative number) or lower than
budgeted (with a resulting positive number). It measures the actual performance
to date against what’s been spent.
The cost variance (CV) formula is as follows:
CV = EV – AC
For the purposes of the remainder of this section, we’ll
use some example figures so we can show how to calculate each of these
measures. As of December 1, (our measurement date), the performance
measurements are as follows:
PV = 75,000
AC = 71,000
EV = 70,000
Now let’s calculate the CV using these numbers:
70,000 – 71,000 = – 1,000
The result is a negative number, which means that costs
were higher than what was planned for the work that was completed as of December
1. These costs are usually not recoverable. If the result was a positive number,
it would mean that you spent less than what you planned for the work that was
completed as of December 1.
Schedule Variance: Schedule variance, another popular
EVM variance, compares an activity’s actual progress to date to the estimated
progress and is represented in terms of cost. It tells you whether the schedule
is ahead of or behind what was planned for this period. This formula is most
helpful when you’ve used the critical path methodology to build the project
schedule. The schedule variance (SV) is calculated as follows:
SV = EV – PV
Plug in the numbers:
70,000 – 75,000 = – 5,000
The resulting schedule variance is negative, which means
you are behind schedule or behind where you planned to be as of December 1.
Together, the CV and SV are known as efficiency indicators
for the project and can be used to compare the performance of all the projects
in a portfolio.
Performance Indexes
Cost and schedule performance indexes are primarily used to
calculate performance efficiencies, and they’re often used to help predict
future project performance.
The cost performance
index (CPI) measures the value of the work completed at the measurement
date against the actual cost. It is the most critical of all the EVM
measurements according to the PMBOK Guide because it tells you the cost
efficiency for the work completed to date or at the completion of the project.
If CPI is greater than 1, you are spending less than anticipated at the
measurement date. If CPI is less than 1, you are spending more than anticipated
for the work completed at the measurement date.
The cost performance index (CPI) is calculated this way:
CPI = EV / AC
Plug in the numbers to see where you stand:
70,000 / 71,000 = .99
Since the result is less than one, it means cost
performance is worse than expected.
The schedule
performance index (SPI) measures the progress to date against the progress
that was planned. This formula should be used in conjunction with an analysis
of the critical path activities to determine whether the project will finish
ahead of or behind schedule. If SPI is greater than 1, your performance is
better than expected, and you’re ahead of schedule. If SPI is less than 1, you’re
behind schedule at the measurement date.
The schedule performance index (SPI) is calculated this
way:
SPI = EV / PV
Again, let’s see where you stand with this example:
70,000 / 75,000 = .93
Schedule performance is not what you expected as of
December 1.
Estimate at Completion
As your project progresses, you’ll be asked to predict the
total cost of the budget. An estimate at
completion (EAC) is a forecast of the total cost of the project based on
both the current project performance and the remaining work. To understand how
EAC works, you need to know two more terms:
Budget at completion (BAC) is the total amount of the
budget for a work package, a control account, a schedule activity, or the
project.
Estimate to complete (ETC) is the cost estimate for the
remaining project work. This is typically provided by the team members actually
working on the project activities.
EAC is calculated as follows:
EAC = AC + ETC
If you assume your BAC is 300,000 and your ETC is 230,000,
then you can calculate EAC as follows:
71,000 + 230,000 = 301,000
As of December 1, our estimate at completion is $301,000,
which is $1,000 more than the budgeted amount (BAC). At this point in the
project, the variance is minimal but should still be a signal to the project
manager to keep a close eye on spending and assure the value delivered matches
the spending to date.
To - Complete Performance Index
To - complete performance index (TCPI) is the projected
performance level that the remaining work of the project must achieve in order
to meet the stated financial or schedule goals. It’s calculated by dividing the
work that’s remaining by the funds that are remaining.
The formula for TCPI is as follows:
(BAC – EV) / (BAC – AC)
Given the measurements as of December 1, here’s the
formula:
(300,000 – 70,000) / (300,000 –
71,000) = 1.0
This means you’ll need to keep performing at the same CPI
rate you’ve experienced to date in order to meet the BAC goal. If the result is
less than one, future work does not have to be performed as efficiently as past
performance. If the result is more than one, future work will have to be
performed more efficiently than past performance in order to meet the BAC goal.
Variance Analysis
Variance analysis is the comparison of planned project
results with actual project results. Variance analysis is most frequently used
to examine the project schedule and project budget. In the Cost Control
process, variance analysis looks at the difference between the performance cost
baseline and actual performance.
The variance at completion (VAC) formula is often used in
this process. It calculates the difference between the budget at completion and
the estimate at completion. The formula is as follows:
VAC = BAC – EAC
Exam nuggets
Be able to name the purpose of the Quality Control process.
The purpose of the Quality Control
process is to monitor work results to determine whether they comply with the standards
set in the quality management plan.
Name the three common causes of variance. These are random variances, known
or predictable variances, and variances that are always present in the process.
Name the tools and techniques for Quality Control. These are histograms, Pareto
diagrams, control charts, statistical sampling, flowcharting, run charts, and
Ishikawa diagrams.
Be able to describe earned value measurement techniques. Earned value measurement (EVM)
monitors the planned value (PV), earned value (EV), and actual costs (AC) expended
to produce the work of the project. Cost variance (CV), schedule variance (SV),
cost performance index (CPI), and schedule performance index (SPI) are the
formulas used with the EVM technique.
Define estimate to complete (ETC), estimate at completion
(EAC), and budget at completion (BAC). Estimate to complete (ETC) is a forecast of the cost of all
remaining project work and is usually provided by the project team members.
Estimate at completion (EAC) is a projection of final project costs obtained by
adding the ETC to the actual project costs to date. Budget at completion (BAC)
is the total amount of the budget for the work package, control account,
schedule activity, or project.
Define the purpose for the Managing Stakeholder
Expectations process. Managing
Stakeholder Expectations involves communicating, resolving issues, improving
project performance by implementing change requests, and managing concerns.
Explain the purpose for the Distribute Information process.
Distribute Information is concerned
with getting stakeholders information about the project in a timely manner. This
is accomplished using status reports, project meetings, review meetings, and so
on, depending on their communication preferences.
Name the types of barriers a project manager might face
when managing teams. Time
zones, language and communication barriers, cultural differences, hierarchical
barriers, and technology barriers are all types of barriers.
10.
Closing the Project
Summary
Project closeout should be performed when the project ends,
when a phase of a project ends, or when a project is killed or canceled. The
Closing process group is the most often skipped on projects because project managers
and team members are anxious to move on to their next assignments. It’s
important to take the time to perform the steps in the Closing process group so
that you can obtain sign-off on the project, turn over the product to the
organization, release project resources, close out the contract, perform a post–project
review, document lessons learned, and create a final project report.
Four types of project endings encompass the majority of
reasons a project comes to an end. They are addition, starvation, integration,
and extinction.
Close Procurements involves completing and settling the
terms of the contract and documenting its acceptance. Product verification
occurs here and that determines whether the work was completed accurately and
satisfactorily.
Administrative Closure involves gathering and centralizing
all the project documents, performing the post-project review, and writing the
final project report.
The post-project review is conducted at the conclusion of
the project, and its primary purpose is to collect and document lessons
learned. Perhaps the most important element of project closure is the lessons
learned document. This entails identifying where things went wrong, what things
went well, and the alternatives you considered during the course of the project.
Lessons learned are an extremely useful reference for future projects regarding
what worked and what didn’t, for estimating techniques, for establishing
templates, and more.
Post-mortem analysis is performed on projects that are
canceled or end prematurely. This is much like the lessons learned process
where information is gathered and recorded regarding what went wrong, the
decisions for cancelation, and the plan for turning over completed
deliverables.
The project close report is distributed to the stakeholders
and includes several elements, including the project’s goal, the statement of
acceptance, a summary of costs and schedule data, and lessons learned data.
Exam nuggets
Name the four reasons for project endings. They are addition, starvation,
integration, and extinction.
Understand the steps involved in closing a project or
phase. The steps
include obtaining sign-off and acceptance, transferring the product to the
organization, releasing project resources, closing out contracts, performing
Administrative Closure, documenting historical information, conducting post-mortem
analysis, and conducting post-project reviews.
Explain the purpose of obtaining formal customer or
stakeholder sign-off. The
formal sign-off documents that the customer accepts the project work and that
the project meets the defined requirements. It also signals the official
closure of the project and the transfer of the final product of the project to
the organization.
Describe transferring the project results to the
organization. Transferring
the project results occurs once sign-off has been obtained. There should be a
documented transition plan for transferring the project results, including
describing the type of training or skills needed to maintain the product.
License costs, warranty coverage and time period, user documentation, and any
other materials needed by the organization should be included in the transfer.
Understand the key elements of the Close Procurements
process. Contract
closeout verifies that all the work described in the contract was completed
satisfactorily per the contract terms and conditions. It includes notifying the
vendor in writing that the work of the contract was accepted.
Name the procedures involved in Administrative Closure. Administrative Closure involves
gathering and centralizing project documents, performing a post-project review,
writing the final project close report, archiving project documents, and
documenting lessons learned and historical information.
Describe lessons learned. Lessons learned describe the
successes and failures of the project.
Good
luck! You will need it.
Thank you so much.
ReplyDeleteStay focused on your core business operations through getting IT managed services London. Avoid getting distracted by IT problems and boost up your business productivity easily!
ReplyDeleteCheck out more at: https://www.thebesgroup.co.uk/
It seems like you're referring to the reasons projects may end based on the text "The Dynamics of Software Development" by Jim McCarthy. Here's an explanation of each reason:
DeleteAddition: Projects end because they have accomplished their objectives or fulfilled their scope. This could mean delivering a product, achieving a milestone, or completing the defined work.
Starvation: Projects end due to lack of resources, funding, or support. When essential inputs like manpower, budget, or management attention are withdrawn or insufficient, the project cannot continue effectively.
Integration: Projects may end because they are integrated into a larger effort or initiative. This could involve merging the project's outcomes or team into another project or organizational structure, thereby concluding its independent existence.
Extinction: Projects end because they are no longer relevant or useful. This could be due to changes in market conditions, technology obsolescence, or shifts in organizational priorities, rendering the project unnecessary or obsolete.
final year projects for computer science
Final Year Project Centers in Chennai
IEEE projects for cse
I wanted to thank you for this great blog! I really enjoying every little bit of it and I have you bookmarked to check out new stuff you post.
ReplyDeleteProject Management
Your site is actually awe-inspiring. I've discovered numerous brand new points. The right path associated with setting up can also be intriguing. You've chosen really amazing subject. We valued this.
ReplyDeleteConsultation manager
This comment has been removed by the author.
DeleteIam very happy after find this post and really thank you. Thanks for sharing this Informative content. Well explained. Got to learn new things from your Blog. I wanted to write a little comment to support you and wish you a good continuation. All the best for all your blogging efforts. To make a project successful project management tools plays an important role. Using Project Management tools is essential and increases the chances of successfully completing the project on time and within the budget, irrespective of the size of the project.
ReplyDeleteTop Agile Project Management Tools
tks
DeleteThank you for this very good and informative post.
ReplyDeleteThis comment has been removed by the author.
DeleteThis comment has been removed by the author.
DeleteThis comment has been removed by the author.
DeleteThis comment has been removed by the author.
DeleteThis is extremely fascinating substance! I have completely delighted in perusing your focuses and have reached the conclusion that you are right about a hefty portion of them. You are extraordinary.
ReplyDeleteBenefits of Enterprise Content Management
Let me share all of you about #10 Tips for Project Management Success, I hope you enjoy it
ReplyDelete1. Plan your day using time management techniques
As a project manager, time management skills are essential because you are dealing with a wide range of tasks that demand a quick turnaround time. Planning your day will go a long way in keeping you organized and increasing your productivity. Assist your task planning by using project management software which helps you track the work of you and your team.
If you are not very tech savvy, a simple to-do list can also be a great organizational tool. Prioritize your most important tasks by putting them at the top of the list and less important ones at the bottom. Having a visual plan of your daily tasks helps to keep you on track and aware of time.
Related post: Free ebook 104 secrets to become a great project manager
2. Include stakeholders in important project conversations
While you will have plenty of responsibilities regarding the project, don’t neglect your clients.
Good communication is essential is keeping both parties informed of project progression, curtailing scope creep, and apprised of changing requirements. Some clients may have different expectations when it comes to communication, so make sure to establish the frequency and type of communication (like emails, phone calls, and face-to-face conversations) at the beginning of your project.
Establishing communication expectations early helps alleviate stakeholder uncertainty about communication frequency and delivery.
3. Regularly communicate with your team
Daily team communication helps keep misunderstandings and unclear requirements under control. Keeping your team informed in every step of the project is essential to project management success.
For example, a study published by Procedia Technology found that good communication skills were the cornerstone of project management. The study examined over 300 “construction project managers, architects, construction managers, engineers and quantity surveyors” and their successes and failures on various construction projects.
4. Anticipate project setbacks
Even the best-laid plans often go awry.
Remember that even with a high amount of planning and attention to detail, your project may still encounter some challenges. Pay attention to complaints from stakeholders or colleagues, and other warning signs, like a missed deadline or cost overrun, that there may be a problem.
Preventing a crisis will keep your project running smoothly, save you a lot of time, and keep you, your team, and your stakeholders confident in progressing with the project.
Unfortunately not every complication can be avoided. Crisis management skills are essential for dealing with the unexpected. Project managers need to be flexible and pragmatic. Improvise and make sharp decisions when needed.
Related post: 92 free project management templates
5. Stay focused on the details
A common problem project managers encounter is having the project aims not aligned with the organization’s objectives. A great project manager will strategize a plan for the project to lead back to the overall success of the business.
Know your project’s scope by heart and avoid wandering outside of the project’s requirements. It’s too easy to get lost in minor details and forget what your focus is, so a well-planned project scope is essential for success.
And final, you should use KPI to measure effectiveness of the project, here are full list: 76 project management KPIs
Thank you Sir for this summary.
ReplyDeleteInformative post. Thanks for sharing
ReplyDeleteMicrosoftPPM/EPMarrangement
Thanks for the best summary towards CompTIA or PMP project management examinations
ReplyDeleteGREAT WORK
IMPRESSIVE!!!
REALLY APPRECIATE YOUR WORK!!!
Project Management India
the explanation you given to this topic is easy to understand. i need some more details about this topic.
ReplyDeleteHtml5 Training in Chennai
Html5 Courses in Chennai
Html5 Training Institutes in Chennai
Html5 Training in OMR
Html5 Training in Porur
DOT NET Training in Chennai
core java training in chennai
Hibernate Training in Chennai
Mobile Testing Training in Chennai
SAS Training in Chennai
Extraordinary post! I am really preparing to over this data, It's exceptionally useful for this blog.Also incredible with the majority of the significant data you have Keep up the great work you are progressing admirably. I am also writing blogs on project management
ReplyDelete& PMP certification.
This comment has been removed by the author.
ReplyDeleteNice and very informative post regarding project management service..
ReplyDeleteThanks for sharing..
project management service
i love this wedding theme as well a couple and i want to share the also great one Best Event Planners in Pakistan they help to make our event best.
ReplyDeleteNice and very informative post..
ReplyDeleteThanks for sharing..
Construction project management
Agree with the information... Project Management System Software is the application of tools and techniques to organize the project activities to successfully meet the project goals.
ReplyDeleteYes its good tool and nice article. but for implementation need the Project management
ReplyDeleteProject management knowledge provided by PMI.
Project management is the application of processes, methods, skills, knowledge and experience to achieve specific project objectives according to the project acceptance criteria within agreed management parameters. Project management has final deliverable that are constrained to a finite timescale and budget.
ReplyDeleteGreat Information! Its looking Nice. Safety is most important. Useful for me to develop my knowledge. Thank you!
ReplyDeleteCorporate Training Chennai - Safety Training
Nebosh IGC in Chennai
Nebosh Course in Vizag
Nebosh Courses In Chennai
NEBOSH Course in Pondicherry
Industrial Safety Diploma Course In Chennai
Project Management System Software is the best ERP software that makes and manages all the task digitally and helps you in bringing advancement at every level.
ReplyDeleteIt is my great pleasure to visit your website and to enjoy your excellent "project management" post here. I like them very much. I can feel that you paid much attention to those articles, as all of them make sense and are very useful. Thanks so much for sharing.
ReplyDeleteBusiness Consultants in Canada, ERP Solution, Budgeting and Monitoring
You have explained about project management's need and process very effectively. Thanks for sharing !!!! Fahim Moledina is the founder of OptiSyn Consulting which provides- Change, Project Management and Transformation services.
ReplyDeleteThanks for sharing this blog. Fahim Moledina helps us to make project management strategy for creating new business.
ReplyDeleteGreat flow in writing. To be versatile in your project management, learn Prince2 foundation
ReplyDeleteSSbizconsulting is an established firm of experienced and qualified consultants providing business & IT consulting services in Sydney, Australia. We provide project management services and IT consulting services to small and large companies across Sydney. To find out more about our services, please contact us.
ReplyDeletethanks for this blog its very informative for me because i also have a similar content of construction project management in Pakistan
ReplyDelete
ReplyDeleteSuch an informative post. Thank you for sharing
Project Online EPM Implementation
I recommend Team Pro4People :)
ReplyDeleteIf you need help ISO13485 - more information here https://pro4people.com/iso-13485-medical-devices-certified-quality-management-system/
Nice blog !!!
This topic has always been one of my favorite subjects to read about Project management services. I have found your post to be very rousing and full of good information . Thank you for providing useful information
ReplyDeleteThank you for being supportive by sharing your own thoughts and ideas with us. Please keep sharing such information.
ReplyDeleteConstruction accounting services in London
ReplyDeleteSearching and reading about the faility management services is my favourite topic. Thank you for providing full of informative blog. I would love to read more on this topic.
Industrial Training in Noida
ReplyDeleteI am learning pmp, this is very good information to learn more about other topics also. i am waiting for more articles by the same author thank you for valuable information pmp certification
ReplyDeleteIt is my great pleasure to visit your website and to enjoy your excellent post here. I like them very much. I can feel that you paid much attention to those articles, as all of them make sense and are very useful. Thanks so much for sharing.
ReplyDeleteAccounting and Bookkeeping services Mississauga
Most wonderfull Article, Thanks for sharing!
ReplyDeleteWrike: The Online Project Management Software / Tools
Learn how to control cost in project management and how to do a construction take off with our self paced courses.
ReplyDeleteProviding the best project management services to customers is a challenge now. After reading your article all the confusion has gone. These points you have shared in your blog are very beneficial for the project manager. I've learned from your guide, it's very simple but effective writing. Thank you.
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteIt is my great pleasure to visit your website and to enjoy your excellent post here. I like them very much. I can feel that you paid much attention to those articles, as all of them make sense and are very useful. Thanks so much for sharing.
ReplyDeleteBusiness consultants in Canada
Your blog is really good and informative. These Online Project Management tools are easy to handle and easy to track the data.
ReplyDeleteYou truly did more than visitors’ expectations. Thank you for rendering these helpful, trusted, edifying and also cool thoughts on the topic.
ReplyDeleteProcurement Management Software
Purchase Management Software
e Procurement Management Software
Procurement Tracking Software
You've made some good points there.I was able to find good information from your blog articles, it's very useful Information about this topic "Time Tracking Software "
ReplyDeleteI am curious to find out what blog system you're utilizing? I'm experiencing some minor security issues with my latest website and I would like to find something more secure. Do you have any recommendations?
ReplyDeleteworkplace governance systems Perth
M3M Golf Estate Providing Ready to Move Golf Facing Apartments in Gurgaon for sale with Eco-friendly Landscapes Equipped With High-End Luxury & Furnishing. Book Now!
ReplyDeleteDLF The Ultima Gurgaon is Ready To Move project. DLF Builders offers Residential Properties in DLF The Ultima. Snap for Project Price List, Map, Photos, Videos, Reviews, Location Highlights & Nearby comparative projects on dlftheultimas.in.
ReplyDeleteVery informative post! This post gives truly quality information. I find that this post is really amazing. Thank you for this brief explanation and very nice information.
ReplyDeleteAOL Mail Inbox
I was curious if you ever thought of changing the layout of your site? Its very well written; I love what youve got to say. But maybe you could a little more in the way of content so people could connect with it better. Youve got an awful lot of text for only having 1 or 2 images. Maybe you could space it out better?
ReplyDeleteworkplace governance systems Perth
Thanks for sharing such a great information to me.
ReplyDeleteISO 22301 Certification Bahrain
Thanks for providing these kinds of Information about Time Tracking software. This post is very useful for me I bookmark this and I hope your next article coming soon
ReplyDeleteVisit here :- Time Tracking Tool
You have provided informative details.
ReplyDeleteERP Gold| https://www.erp.gold/
Nice blog! Your blog unique and very informative for everyone. If you are looking for quality training courses then knowledgekafe is best for you. Here you enroll and attend training courses like project management course, MS office online course , Arabic speaking classes Social media marketing courses and so on.
ReplyDeleteBrilliant put up your article is admirable and full of detail. I was really impressed with your interesting blog and the plenty in the content. Thanks for sharing.
ReplyDeleteVisit here :- Project Tracking Software
Really nice and informative..I found this blog very useful. Quantity surveyors in UAE
ReplyDeleteThanks for sharing this post. We deliver, manage the complete process which includes the discipline of project planning, project monitoring, managing resources & subcontractors and supporting design deliverables. we are one the best Project management Consultants in UAE. for more information you can contact +971 6 557 3924. Project management Consulting Services
ReplyDeleteWow what a great post.It provides a brief information about Project Management Consultants. But if you are looking for the Services in UAE . Visit us at yellowpages.ae
ReplyDeleteI am really lucky that I found your website by mistake, really useful information about Project Management. Thanks for this informative information and I bookmarked it.
ReplyDeleteVisit: Time Tracking Software
TC Consultancy specializes in customizing its approach for diverse construction projects as per the needs and challenges of each project, irrespective of its size and scope. We specialize, best in Quantity Surveying Services .Project Management, Project Development, Tenancy and Facility Support Management. for more information you can contact +971 6 557 3924
ReplyDeleteWe deliver, manage the complete process which includes the discipline of project planning, project monitoring, managing resources & subcontractors and supporting design deliverables. we are one the best Project management Consultants in UAEProject management Consulting Services .for more information you can contact +971 6 557 3924.
ReplyDeleteGreat post, thanks for sharing this article. I am really interested in your blog.
ReplyDeleteproject management consultants in uae,project management consultancy services
The development has a vital role in any part of the world, especially in the United Arab Emirates. The infrastructure of a country uncovers the budgetary wealth and the living status of individuals. There are various kinds of construction companies in Dubai such as concrete structures, Steel outline structures, Light gauge steel, wood-framed development, load-bearing construction, solid development, pre-designed structures, mechanical structure, and 3d printed building.
ReplyDeleteconstruction companies in Dubai list
The development has a vital role in any part of the world, especially in the United Arab Emirates. The infrastructure of a country uncovers the budgetary wealth and the living status of individuals. There are various kinds of construction companies in Dubai such as concrete structures, Steel outline structures, Light gauge steel, wood-framed development, load-bearing construction, solid development, pre-designed structures, mechanical structure, and 3d printed building.
ReplyDeleteAll Construction Companies in UAE
We deliver, manage the complete process which includes the discipline of project planning, project monitoring, managing resources & subcontractors and supporting design deliverables. we are one the best Project management Consultants in UAEProject management Consulting Services in Saudi arabia .for more information you can contact +971 6 557 3924.
ReplyDeleteTC Consultancy has extensive experience of providing a total Project development for all types Services of building, transportation, power, defence etc. for more information you can contact +971 6 557 3924
ReplyDeleteProject Development Sharjah
I have read your article, it is very informative and helpful for me.I admire the valuable information you offer in your articles. Thanks for posting it.. https://westasianetwork.com/ashford-formula-united-arab-emirates.php
ReplyDeleteThanks for sharing this great content. It is really informative and useful. You can also check this Similar site for PMP course.
ReplyDeleteI was searching for a proper explanation anti money laundering certification free. Thanks, admin, for sharing such wonderful content on this topic. Now I have got everything I need about it. Here’s another informative content on. Anti Money Laundering Certification Free You will get well researched information about it.
ReplyDeleteNice Content.
ReplyDeleteAn advise to all who are planning to obtain a PMP Certification. As much as possible, enroll your self with ATP. Enjoy the benefits from Premium PMI Authorized Training Partner. By choosing an unapproved training provider, you might waste your time, resources, and money. For example, many unapproved institutes’ training material is a copy and paste of the PMBOK(r) Guide. However, the PMP 2021 exam is completely different with 50% of the exam questions focusing on Agile practice and 3 domains (People, Process, and Business Environment). Should you need Free Consultation for PMP or any certification like ASQ-CMQ /OE, please contact me : Mobile: +971.56.9012099 Email ID: Alegria@3foldtraining.com
Thanks for sharing the great information. Keep up the good work.
ReplyDeleteProject Management Companies Sydney
Project Management Consultancy Sydney
#
ReplyDeletePMP CERTIFICATION
This comment has been removed by the author.
ReplyDeleteNice post, thanks for sharing...!!
ReplyDeleteWant to know about PMP Certification Training ? MindCypress is here at your service. Project Management is a vast subject that helps in the growth process of a company. We ensure to serve you with ample amount of knowledge and assist you in using your skills wisely.
Nice blog thanks for sharing
ReplyDelete#FIDIC CERTIFICATION
Thanks for sharing such a nice post with lot of content..FIDIC
ReplyDeleteThis blog is very informative thanks for sharing and keep on posting .#ISO CERTIFICATION
ReplyDelete#lead auditor course
The information you have provided about Time Tracking Software is excellent, and I have gained a lot of knowledge. Hopefully, you will continue to share interesting content about this topic.
ReplyDeleteVisit: Time Tracking Software
Great Article, Thanks for sharing with us. For Agile Management Software Visit my website: Agile Management Software
ReplyDeleteThank you for providing such great insights in this article, it was very helpful.
ReplyDeletefor more information regarding Project management certification courses please get in touch with 360DigiTMG team.
PMP Certification course
Hey thanks for sharing a great article post in this page its very important for me. You can visit here for Drainage and irrigation companies near me
ReplyDeleteproject management consultancy firms
cpm advisory and project management
project management advisory services
I have visited many websites but this is the best so far. I have learned a lot from this post which will help me a lot in future. Plan Management
ReplyDeleteFantastic Article!! I came on your blog and discovered a wealth of knowledge regarding project management software products. Thank you for sharing this data. I'm hoping you'll keep sharing interesting article on this subject.
ReplyDeleteThanks for sharing. Visit to Dnetsoft website for ERP for Construction Company
ReplyDeleteThanks for sharing this informative bog about project management I find this very useful for my study as well which isPGDM in operations Keep sharing.
ReplyDeleteThanks for sharing thoughts!
ReplyDeleteProject Management Services Sydney
Nice blog! Thanks for sharing PMP Training
ReplyDeletesafe agilist certification in bangalore
ReplyDeleteThanks for explaining CompTIA or PMP project management examination process in a very easy manner. Upskill yourself in Project Management by exploring Prince2 Certification, prince2 agile certification courses.
ReplyDeleteThanks for sharing the post with us
ReplyDeletedassm
TC Consultancy, as an established project management service provider in Dubai, Sharjah,, Kuwait, Qatar, Bahrain, Oman, KSA. Project management Consulting Services, project monitoring, managing resources & subcontractors and supporting design deliverables to bring about the successful completion of specific project goals and objectives.
ReplyDeleteThanks to the author
ReplyDeleteThanks for this post...BBL Foods provides Project Management Consulting for Innovative food machinery and Food manufacturing machinery besides required engineering services and support for food projects in any volume.
ReplyDelete5 roll refiner machinery
Biscuit Machine manufacturer
Potato chips line supplier
Very nice blog .
ReplyDeleteLeadership Training Mississauga
ReplyDeleteproject management
Project Management is a vital element that chooses the achievement or disappointment of a task. visit our blog to know more-PROJECT MANAGEMENT
PRINCE2 EXAMINATION
ReplyDeletePMP ONLINE COURSE
ReplyDeletePMP Online Training Benefits For Obtaining Your PMP visit our blog to know more-PMP ONLINE COURSE
pmp certification training
ReplyDeletePMP CERTIFICATION TRAINING
Enroll now in PRINCE2 CERTIFICATION
ReplyDelete
ReplyDeletePMP CERTIFICATION COURSE
The PMP course provides managers with the latest information on Project Management norms and practices.Click here to know more PMP CERTIFICATION
Hey, If you want to know some - requirement for pmp certification Then you should check this out
ReplyDeletewonderful Post.
ReplyDeletehttps://www.knowlathon.com/blog/how-to-do-pmp-certification/
This information you have supplied is incredibly useful. It's great that this since it helps us and increases our knowledge. I'm grateful you shared this article. asset inventory management software
ReplyDeleteI was searching about the pmp training in karachi for a long time. Your blog has the valueable information about the topic. I've learned many good points from your blog. Thank you and keep writing.
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteThanks for sharing a valuable information & love to hear from you soon!
ReplyDeleteConstruction document management software
Nice informative post!
ReplyDeleteHey, nice blog, I found many things that are very informative.
ReplyDeleteBiobanks | biorepositories
human-samples | patient-samples
Bhurban Meadows prioritizes sustainability, making it a future-ready investment with a focus on eco-friendly practices.
ReplyDeleteLuxury Cottages in Bhurban
Empro group Does handle project management as its core service.
ReplyDeleteThanks for sharing this very good write-up. Very interesting ideas! (as always)
ReplyDeleteSAP QM S4 HANA Online Training from USA, Uk, Australia, UAE, Canada
Best Powershell Training
Windows Server Training from UK
PHP Developer Online Training from USA
Apache Spark Online Training
RPA Online Coaching from Canada
SAP Spartacus Online Course from Malaysia
Linux Administration Training Course In Hyderabad