Project Management

Hello.

Here is a summary of all you need to know towards CompTIA or PMP project management examinations.

1.     Initiating a project
Summary
A project is a temporary endeavor that produces a unique product, service, or result. It has definitive start and finish dates.
Project management is the application of tools and techniques to organize the project activities to successfully meet the project goals.
A project manager is responsible for project integration and applying the tools and techniques of project management to bring about a successful conclusion to the project.
Organizational structures impact how projects are managed and staffed. The primary structures are functional, matrix, and project-based. The traditional departmental hierarchy in a functional organization provides the project manager with the least authority. The other end of the spectrum is the project - based organization, where resources are organized around projects; in these types of organizations, the project manager has the greatest level of authority to take action and make decisions regarding the project. The matrix organization is a middle ground between the functional organization and the project - based organization.
Project selection techniques involve the use of decision models, such as a cost - benefit analysis and expert judgment, to allocate limited resources to the most critical projects.
Project managers are individuals charged with overseeing every aspect of a given project from start to finish. A project manager needs not only technical knowledge of the product or service being produced by the project, but also a wide range of general management skills.
Key general management skills include leadership, communication, problem solving, negotiation, organization, and time management.
Exam Nuggets
Be able to define a project. A project brings about a unique product, service, or result and has definite beginning and ending dates.
Be able to identify the difference between a project and ongoing operations. A project is a temporary endeavor to create a unique product or service. Operational work is ongoing and repetitive.
Be able to understand the three types of organizational structures. The three types of organizational structures are functional, matrix, and project - based structures. Matrix organizations may be structured as a strong matrix, weak matrix, or balanced matrix organization.
Be able to define the role of a project manager. A project manager’s core function is project integration. A project manager leads the project team and oversees all the work required to complete the project goals to the satisfaction of the stakeholders.
Be able to identify the most common project selection methods. The most common project selection methods are benefit measurement methods such as cost - benefit analysis, scoring models, payback period, and economic models (which include discounted cash flows, NPV, and IRR), as well as expert judgment.
Understand what skills are needed to manage a project beyond technical knowledge of the product. Key general management skills include leadership, communication, problem solving, negotiation, organization, and time management
 2.  Project Process Groups and the Project Charter
Summary
Collectively, project management consists of five process groups: Initiating, Planning, Executing, Monitoring and Controlling, and Closing. Each of these process groups consists of individual processes that each have inputs, tools and techniques, and outputs. The primary output of the Initiating process group is the project charter.
Initiation is the formal authorization for the project to begin. It starts with a project request that outlines the high - level requirements, or the product description. There are three types of requirements: functional, business, and technical.
A Project stakeholder is anyone who has a vested interest in the outcomes of the project. Some project stakeholders you will likely encounter include the project sponsor, team members, functional managers, customers (both internal and external), and end users.
A project sponsor is an executive in the organization who has the authority to assign budget and resources to the project. Project sponsors serve as final decision makers on the project and sign and approve the project charter.
The output from the Initiating process is the project charter. This document becomes the basis for more-detailed project planning. It should contain the project description, project approach, stakeholders, goals and objectives, problem statement, high - level deliverables, milestones, costs, assumptions, constraints, and risk.
Exam nuggets
Be able to define the Initiating process. Initiation authorizes the project to begin.
Understand the three categories of requirements. Functional requirements define how the user will interact with the system. Business requirements are the big picture of what the business wants from the system. Technical requirements define what the system does to perform the functional requirements.
Be able to define a project sponsor and the stakeholders’ common to most projects. A project sponsor is an executive in the organization who has the authority to allocate funds and resources to the project.
A stakeholder is an organization or someone who has a vested interest in the project and has something to gain or lose from the project. Stakeholders include the sponsor, project manager, project team members, functional managers, customer, end users, and others with an interest in the project.
Be able to describe a project charter and list the key components. A project charter provides formal approval for the project to begin and authorizes the project manager to apply resources to the project. The key components are the problem statement, deliverables, milestones, costs, assumptions, constraints, risks, stakeholders, and project description.
3.  Planning a Project
Summary
Scope planning uses the output of the Initiating process, the project charter, to create the scope statement and the scope management plan. The scope management plan documents the process you’ll use to prepare the project scope statement and WBS, a definition of how the deliverables will be verified, and a description of the process for controlling scope change requests.
The project scope statement is the basis for many of the planning processes and future change decisions. It is also the basis for setting the boundaries of the project with the customer and stakeholders. A scope statement includes the product description, key deliverables, success and acceptance criteria, key performance indicators, exclusions, time and cost estimates, assumptions, and constraints.
The work breakdown structure (WBS) is created by taking the major deliverables from the scope statement and decomposing them into smaller, more manageable components. The breakdown continues through multiple levels until the components can be estimated and resourced. The lowest level of decomposition is the work package. The WBS includes all the work required to complete the project. Any deliverable or work not listed on the
WBS is assumed to be excluded from the project. The WBS is a critical component of project planning. A WBS is the basis for time estimates, cost estimates, and resource assignments.
The WBS dictionary should list every deliverable and each of their components contained in the WBS. It should include a description of the component, code of account identifiers, responsible party, estimates, criteria for acceptance, and any other information that helps clarify the deliverables and work components.
Exam nuggets
Describe the purpose of a scope management plan. A scope management plan documents the procedures for preparing the project scope statement and WBS, defines how the deliverables will be verified, and describes the process for controlling scope change requests.
Understand the purpose of the scope statement. The scope statement is the basis of the agreement between the project and the customer concerning what comprises the work of the project. It defines the deliverables and success criteria that will meet those objectives.
Be able to list the components of a scope statement. A scope statement includes a product description, key deliverables, success and acceptance criteria, key performance indicators, exclusions, assumptions, and constraints.
Know how to define and create a work breakdown structure (WBS). The WBS is a deliverable - oriented hierarchy that describes the work required to complete the project. The WBS is a multilevel tree diagram that starts with the project, includes the major deliverables, and decomposes the major deliverables into smaller units of work to the point where time and cost estimates can be provided and resources assigned.
Understand the levels in a WBS. The highest level of the WBS is the project name. The major deliverables, project phases, or subprojects make up the next level. The number of levels in a WBS will vary by project; however, the lowest level of the WBS is a work package.
Describe a WBS dictionary. The WBS dictionary describes each of the deliverables and their components and includes a code of accounts identifier, estimates, resources, criteria for acceptance, and any other information that helps clarify the deliverables.
4.  Schedule Planning
Summary
Many steps are involved in schedule planning. Activity Definition takes the work packages from your WBS and breaks them down into assignable tasks. Activity Sequencing looks at dependencies between tasks. These dependencies can be mandatory, discretionary, or external. A dependent task is either a successor or a predecessor of a linked task. There are four types of logical relationships: finish-to-start, start-to-start, start-to-finish, and finish-to-finish. A network diagram is a pictorial representation of the task-dependency (logical) relationships.
Activity Duration estimating is obtained using analogous (also called top - down) estimating, parametric estimating, expert judgment, three - point estimates, and PERT.
The most complex schedule planning process is Schedule Development. The critical path method (CPM) creates a schedule by calculating forward and backward passes through the network diagram and then determining float.
Float is the difference between the early and late start dates and the early and late finish dates. The critical path is the longest full path on the project.
Duration compression is the technique used to shorten a project schedule to meet a mandated completion date. Crashing shortens task duration by adding more resources to the project. Fast tracking is where two tasks are started in parallel that were previously scheduled to start sequentially.
A project schedule may be displayed as a milestone chart. Milestones mark major project events such as the completion of a key deliverable or project phase. Gantt charts are a common method to display schedule data as well. The completed, approved project schedule becomes the baseline for tracking and reporting project progress.
Exam nuggets
Describe the Activity Sequencing process. Activity Sequencing is the process of identifying dependency relationships between the project activities and scheduling activities in the proper order.
Name the two major relationships between dependent tasks. A predecessor is a task that exists on a path with another task and occurs before the task in question. A successor is a task that exists on a common path with another task and occurs after the task in question.
Name the four types of logical relationships. The four types of logical relationships are finish-to-start, start-to-start, start-to-finish, and finish-to-finish.
Know and understand the five most commonly used techniques to estimate activity duration. Expert judgment relies on the knowledge of someone familiar with the tasks. Analogous or top - down estimating bases the estimate on similar activities from a previous project. Parametric estimates are quantitatively based estimates that typically calculate the rate times quantity. Three - point estimates use the most likely, optimistic, and pessimistic estimates to determine an average estimate. PERT uses the same estimates as the three – point estimating technique, but it calculates an expected value or weighted average estimate.
Define the purpose of CPM. CPM calculates the longest path in the project. This path controls the finish date of the project. Any delay to a critical path task will delay the completion date of the project.
Explain a network diagram. A network diagram is used in Activity Sequencing to depict project activities and the interrelationships and dependencies among these activities.
Name the two most common ways project schedules are displayed. Project schedules are typically displayed as milestone charts or Gantt charts; a Gantt chart is a type of bar chart.
5.  Communication, Human Resources & Quality Plan
Summary
Most project managers spend the majority of their project management time in the act of communicating. Communication is performed using the sender - message – receiver model. Communications Planning is a process where you determine who needs what types of communication, when, and in what format, and how that communication will be disseminated. The network communication model shows the lines of communication that exist between any number of project participants.
Resource Planning involves determining all the materials, goods, equipment, and human resources you’ll need to perform the work of the project. You can depict the roles and responsibilities of human resources graphically in a RAM or a RACI chart.
Human Resource Planning identifies the specific resources that will be assigned to your project as well as how and when they will join the project team and be returned to their functional department. You’ll document the resources needed in the human resource management plan. Be aware of constraints that may impact the human resource management plan, such as labor union agreements, organizational structure, and economic conditions.
Staff acquisition is where you choose the team members (or organizations) who will work on the project. You should be prepared to negotiate with functional managers for resources and also be prepared to interview potential team members to determine experience levels, skill, and overall fit on the team.
Procurement planning is performed when goods or services for the project will be provided outside the organization. Procurement planning involves a make - or - buy analysis, SOW preparation, vendor solicitation, and vendor selection criteria. The typical solicitation vehicles for contracting include an RFQ, RFP, and RFI or IFB.
Exam nuggets
Describe the importance of Communications Planning. Communications Planning is the key to project success. It involves determining who needs information, when, and in what format, and the frequency of the communication.
Describe Resource Planning. Resource Planning determines what resources are needed for the project, including human, equipment, and material.
Describe a RAM. A RAM is a resource assignment matrix that shows the WBS identifier, the type of resource required, and the number of resources for each skill set. A RACI chart is a type of RAM that describes the resources and their level of responsibility, including responsible, accountable, consult, or inform.
Describe the two components of Human Resources Planning. The two components are organizational planning and staff acquisition.
Be able to describe make - or - buy analysis. Make - or - buy analysis is performed in order to determine the cost-effectiveness of either making or buying the goods and services you need for the project.
Be able to name the types of contracts. The contract types include fixed-price, cost- reimbursable, and time and materials.
6.  Defining the Cost, Quality, and Risk Plans
Summary
The Cost Estimating process is performed after the resources for the project have been determined. You can use several techniques to create project estimates.
Ø Analogous or top - down estimates use expert judgment and historical data to provide a high - level estimate for the entire project, a phase of the project, or a deliverable.
Ø Parametric estimating uses a mathematical model to create the estimates and, in its simplest form, multiplies the duration of the project task by the resource rate to determine an estimate.
Ø The bottom - up method creates the project estimate by adding up the individual estimates from each work package.
Cost estimates are used to make up the project budget. The project budget is established by using the organization’s chart of accounts and then documenting work effort, duration, equipment and material costs, and any other costs that may be incurred during the course of the project.
The cost baseline is the total approved expected cost for the project and is used for forecasting and tracking expenditures throughout the project.
Quality Planning identifies the quality standards that are applicable to the project and determines how the project will meet those standards. Some of the most common tools used in Quality Planning include cost - benefit analysis, benchmarking, flowcharting, and cost of quality.
Cost of quality is the total cost of all the work required to assure the project meets the quality standards. There are three types of quality costs: prevention, appraisal, and failure costs.
Risk Planning involves identifying potential risk events that could occur during the project, determining their probability of occurrence, and determining their impact to the project.
Probability is always expressed as a number between 0.0 and 1.0. Risk response plans should be developed for those risks that have a high probability of occurrence, have a significant impact to the project if they occur, or have an overall risk score that is high.
Risks must be analysed, qualitatively and quantitatively. Qualitative risk analysis involves multiplying the probability that a risk will occur by the impact when it occurs to create risk exposure. Quantitative risk analysis involves ranking of risks and finding their cost and time contingencies.
The final project management plan consists of all the documents created during the planning phase of the project. It’s good practice to obtain sign - off on the project plan from the sponsor and key stakeholders before proceeding. Once approval is obtained, the project management plan becomes the baseline for the project.
Exam nuggets
Know the difference between analogous, parametric, and bottom - up estimating techniques. Analogous, or top - down, estimates use expert judgment and historical data to provide a high - level estimate for the entire project, a phase of the project, or a deliverable. Parametric estimates use a mathematical model to create the estimates. The bottom - up method starts at the lowest level of the WBS and calculates the cost of each item within the work packages to obtain a total cost for the project or deliverable.
Name the two discretionary funding allocations a project may receive. The two types of discretionary funding are a contingency reserve and a management reserve. Contingency reserves are monies set aside to cover the cost of possible adverse events. Management reserves are set aside by upper management and are used to cover future situations that can’t be predicted during project planning.
Explain the purpose of a cost baseline. The cost baseline is the total approved, expected cost for the project. It’s used in the Executing and Monitoring and Controlling processes to monitor the performance of the project budget throughout the project.
Name the Quality Planning tools and techniques. The Quality Planning tools and techniques are cost - benefit analysis, benchmarking, flowcharting, and cost of quality.
Name the types of costs associated with the cost of quality. The types of costs associated with the cost of quality are prevention costs, appraisal costs, and failure costs. Failure costs include both internal and external failure costs.
Explain the three processes used to develop a risk management plan. Risk Identification is the process of identifying and documenting the potential risk events that may occur on the project. Risk analysis evaluates the severity of the impact to the project and the probability that the risk will actually occur. Risk response planning is the process of reviewing the list of potential risks impacting the project to determine what, if any, action should be taken and then documenting it in a response plan.
Name the negative risk response strategies. The negative risk response strategies are avoid, transfer, mitigate, and accept.
Name the positive risk response strategies. The positive risk response strategies are exploit, share, and enhance.
7.  Processing Change Requests
Summary
As is peculiar in all aspects of existence, things change. Changes come about for many reasons and may take the form of corrective actions, preventive actions, and defect repairs.
An integrated change control system manages change requests, determines the global impacts of a change, and updates all impacted portions of the project plan when a change is made. Typically, a change control board is established to review and either approve, deny, or delay change requests.
Scope Control involves reviewing and analyzing requests for scope changes, and updating the scope baseline documents if a scope change occurs. The scope baseline consists of the scope statement, WBS, and WBS dictionary.
Scope Verification is the process of formally accepting the deliverables of the project and obtaining sign - off from the stakeholders that they’re complete and acceptable.
Schedule Control involves determining the status of the project schedule, determining whether changes have occurred or should occur, and influencing and managing schedule changes. Particular emphasis should be placed on monitoring critical path tasks. Schedule updates may be required as a result of a schedule change. Schedule compression techniques (fast-tracking and crashing) can be used to help manage schedule changes.
Risk Monitoring and Control is when the risk response plans identified during planning are implemented if needed. Other activities that occur in this process include identifying and prioritizing new risks, implementing contingency plans based on a trigger event, and evaluating the effectiveness of response plans.
Reporting Performance is the process that involves collecting information regarding project progress and project accomplishments and reporting it to the stakeholders. Any project element that goes outside predefined limits requires action on the part of the stakeholder team. Trade - offs between quality, scope, schedule, and cost are presented by the project manager.
Cancellation of the project is also an action for consideration if the project is no longer viable.
Exam nuggets
Name and describe the three types of change requests. Corrective actions bring the work of the project into alignment with the project plan, preventive actions are implemented to help reduce the probability of a negative risk event, and defect repairs correct or replace components that are substandard or malfunctioning.
Describe the possible impacts to check for when evaluating a major change to the project scope. A major change to the project scope may impact the critical path, schedule end date, budget, and resources, as well as introduce new risks.
Describe the elements of a change management process. The elements of a change management process include change request forms, a change request log, analysis of changes, the CCB, coordination and communication with stakeholders, and updating the affected project planning documents.
Explain the purpose of a CCB. The change control board reviews, approves, denies, or delays change requests.
Describe the purpose for the Scope Control process. Scope Control involves monitoring the status of the project scope, monitoring changes to the project scope, and monitoring work results to ensure that they match expected outcomes.
Describe the purpose for the Scope Verification process. Scope Verification involves formally accepting completed deliverables and obtaining sign - off from the stakeholders indicating the deliverables are satisfactory and meet the stakeholders’ expectations.
Describe the purpose for the Schedule Control process. Schedule Control involves determining the status of the project schedule, determining whether changes have occurred or should occur, and influencing and managing schedule changes.
Describe the Risk Monitoring and Control Process. Risk Monitoring and Control is the process of implementing the risk response plan, tracking and monitoring identified risks, and identifying and responding to new risks as they occur.
8.  Executing the Project
Summary
Project execution is an exciting time because you finally get to see results of the hard work from the Initiating and Planning processes. But just because you are executing against a well - defined plan does not mean that you can sit back and watch the project pieces fall into place. You have a lot of work to do in this phase, including assembling and motivating the project team, holding the kickoff meeting, and determining the organizational oversight needed for the project.
Staffing issues may arise with the functional managers who provided you with resources for the project. You should attempt to resolve these issues with the functional manager directly, but if a compromise can’t be reached, escalation to the sponsor may be required.
Successful team development includes ongoing team building and management, training, and a meaningful rewards and recognition system. It’s also a time to build and establish an open, trusting environment and to encourage the free exchange of ideas.
As the work on the project progresses, you need to collect data from team members regarding their progress on the project and prepare status reports for the sponsor and stakeholders. It’s always important to understand any rules, regulations, or internal processes that you should adhere to when executing the work of the project.
Exam nuggets
Name some of the common causes of conflict. Common causes are competing resource demands, expert judgment, and varying work styles.
Name the conflict - resolution techniques. The techniques are smoothing, forcing, compromise, confronting, avoiding, and negotiating.
Name the conflict - resolution technique most often used by project managers. This is confronting, also known as problem solving. This technique involves discovering the facts regarding the issue and letting the facts help define the solution.
State the five stages of team development. They are forming, storming, norming, performing, and adjourning.
Understand the various means to recognize or reward team members. Team member contributions can be recognized with monetary rewards or prizes, a mention in the formal project review or status meeting, a letter to executive management, a thank - you, or a team celebration.
State the purpose of a project kickoff meeting. The project kickoff meeting is a way to formally introduce all project team members, to review the goals and the deliverables for the project, to discuss roles and responsibilities, and to review stakeholder expectations.
Explain the importance of organizational governance. Organizational governance recognizes the importance of regulations, laws, and other standards that may impact the project. This also involves internal processes, version control, and checkin/checkout processes.
9.  Controlling the Project
Summary
Quality Control is the process of reviewing project results and determining whether they comply with the standards documented in the quality management plan and making any appropriate changes to remove the causes of unacceptable quality when the standards are not met. Quality Control is performed throughout the life of the project. You can use several tools and techniques to perform Quality Control, including inspection, prevention, histograms, Pareto diagrams, control charts, statistical sampling, flowcharting, trend analysis, run charts, and Ishikawa diagrams.
Quality Control concerns identifying variances in the process or results. There are three common causes of variance: random variances, known or predictable variances, and variances that are always present in the system.
Cost Control involves managing changes to the project cost baseline. It’s also concerned with monitoring project budgets to prevent unauthorized or incorrect costs from getting included in the cost baseline.
Earned value measurement is a tool and technique that measures the value of the work completed to date by comparing what you’ve received or produced to what you’ve spent as of the measurement date by using measurements such as CV, SV, CPI, SPI, ETC, and EAC.
Managing Stakeholder Expectations involves making sure certain communication needs and expectations of the stakeholders are met, managing any issues stakeholders might raise that could become future issues, and resolving previously identified issues. One of the ways to manage expectations is to manage the information distribution process.
The Distribute Information process is concerned with making certain project information available to stakeholders at the right time and in the appropriate format. Distribute Information is performed throughout the life of the project.
Managing team members involves being aware of barriers and differences that may impact communication and the productivity of the team, including different time zones, communication and language barriers, cultural differences, technology barriers, and hierarchical barriers.
Earned Value Measurement
EVM looks at schedule, cost, and scope project measurements together and compares them to the actual work completed to date. It is the most often used performance measurement method. EVM is performed on the work packages and the control accounts of the WBS. To perform the EVM calculations, you need to first gather these three measurements: planned value, actual cost, and earned value.
Planned value: The planned value (PV) is the cost of work that has been authorized and budgeted for a schedule activity or WBS component during a given time period or phase. These budgets are established during the Planning processes. PV is also known as the budgeted cost of work scheduled (BCWS).
Actual cost: Actual cost (AC) is the actual cost of completing the work component in a given time period. Actual costs might include direct and indirect costs but must correspond to what was budgeted for the activity. If the budgeted amount did not include indirect costs, do not include them here. Later you’ll see how to compare this to PV to come up with variance calculation results. AC is also known as the actual cost of work performed (ACWP).
Earned value Earned value (EV) is the value of the work completed to date as it compares to the budgeted amount (PV) for the work component. EV is typically expressed as a percentage of the work completed compared to the budget. For example, if our budgeted amount is ₦1,000 and we have completed 30 percent of the work so far, our EV is ₦300. Therefore, EV cannot exceed the PV budget for the activity. EV is also known as the budgeted cost of work performed (BCWP).
PV, AC, and EV all include a cost component. When costs are displayed graphically, they form an S curve. The reason for this is that at the beginning of the project, spending is minimal; then it picks up once the work of the project is underway, and it tapers off at the end of the project as the work wraps up. Since earned value measurements include a cost component, they are also displayed in an S curve.
Cost Variance: Cost variance is one of the most popular EVM variances that project managers use. It tells you whether your costs are higher than budgeted (with a resulting negative number) or lower than budgeted (with a resulting positive number). It measures the actual performance to date against what’s been spent.

The cost variance (CV) formula is as follows:
CV = EV – AC
For the purposes of the remainder of this section, we’ll use some example figures so we can show how to calculate each of these measures. As of December 1, (our measurement date), the performance measurements are as follows:
PV = 75,000
AC = 71,000
EV = 70,000
Now let’s calculate the CV using these numbers:
70,000 – 71,000 = – 1,000
The result is a negative number, which means that costs were higher than what was planned for the work that was completed as of December 1. These costs are usually not recoverable. If the result was a positive number, it would mean that you spent less than what you planned for the work that was completed as of December 1.
Schedule Variance: Schedule variance, another popular EVM variance, compares an activity’s actual progress to date to the estimated progress and is represented in terms of cost. It tells you whether the schedule is ahead of or behind what was planned for this period. This formula is most helpful when you’ve used the critical path methodology to build the project schedule. The schedule variance (SV) is calculated as follows:
SV = EV – PV
Plug in the numbers:
70,000 – 75,000 = – 5,000
The resulting schedule variance is negative, which means you are behind schedule or behind where you planned to be as of December 1.
Together, the CV and SV are known as efficiency indicators for the project and can be used to compare the performance of all the projects in a portfolio.
Performance Indexes
Cost and schedule performance indexes are primarily used to calculate performance efficiencies, and they’re often used to help predict future project performance.
The cost performance index (CPI) measures the value of the work completed at the measurement date against the actual cost. It is the most critical of all the EVM measurements according to the PMBOK Guide because it tells you the cost efficiency for the work completed to date or at the completion of the project. If CPI is greater than 1, you are spending less than anticipated at the measurement date. If CPI is less than 1, you are spending more than anticipated for the work completed at the measurement date.
The cost performance index (CPI) is calculated this way:
CPI = EV / AC
Plug in the numbers to see where you stand:
70,000 / 71,000 = .99
Since the result is less than one, it means cost performance is worse than expected.
The schedule performance index (SPI) measures the progress to date against the progress that was planned. This formula should be used in conjunction with an analysis of the critical path activities to determine whether the project will finish ahead of or behind schedule. If SPI is greater than 1, your performance is better than expected, and you’re ahead of schedule. If SPI is less than 1, you’re behind schedule at the measurement date.
The schedule performance index (SPI) is calculated this way:
SPI = EV / PV
Again, let’s see where you stand with this example:
70,000 / 75,000 = .93
Schedule performance is not what you expected as of December 1.
Estimate at Completion
As your project progresses, you’ll be asked to predict the total cost of the budget. An estimate at completion (EAC) is a forecast of the total cost of the project based on both the current project performance and the remaining work. To understand how EAC works, you need to know two more terms:
Budget at completion (BAC) is the total amount of the budget for a work package, a control account, a schedule activity, or the project.
Estimate to complete (ETC) is the cost estimate for the remaining project work. This is typically provided by the team members actually working on the project activities.
EAC is calculated as follows:
EAC = AC + ETC
If you assume your BAC is 300,000 and your ETC is 230,000, then you can calculate EAC as follows:
71,000 + 230,000 = 301,000
As of December 1, our estimate at completion is $301,000, which is $1,000 more than the budgeted amount (BAC). At this point in the project, the variance is minimal but should still be a signal to the project manager to keep a close eye on spending and assure the value delivered matches the spending to date.
To - Complete Performance Index
To - complete performance index (TCPI) is the projected performance level that the remaining work of the project must achieve in order to meet the stated financial or schedule goals. It’s calculated by dividing the work that’s remaining by the funds that are remaining.
The formula for TCPI is as follows:
(BAC – EV) / (BAC – AC)
Given the measurements as of December 1, here’s the formula:
(300,000 – 70,000) / (300,000 – 71,000) = 1.0
This means you’ll need to keep performing at the same CPI rate you’ve experienced to date in order to meet the BAC goal. If the result is less than one, future work does not have to be performed as efficiently as past performance. If the result is more than one, future work will have to be performed more efficiently than past performance in order to meet the BAC goal.
Variance Analysis
Variance analysis is the comparison of planned project results with actual project results. Variance analysis is most frequently used to examine the project schedule and project budget. In the Cost Control process, variance analysis looks at the difference between the performance cost baseline and actual performance.
The variance at completion (VAC) formula is often used in this process. It calculates the difference between the budget at completion and the estimate at completion. The formula is as follows:
VAC = BAC – EAC
Exam nuggets
Be able to name the purpose of the Quality Control process. The purpose of the Quality Control process is to monitor work results to determine whether they comply with the standards set in the quality management plan.
Name the three common causes of variance. These are random variances, known or predictable variances, and variances that are always present in the process.
Name the tools and techniques for Quality Control. These are histograms, Pareto diagrams, control charts, statistical sampling, flowcharting, run charts, and Ishikawa diagrams.
Be able to describe earned value measurement techniques. Earned value measurement (EVM) monitors the planned value (PV), earned value (EV), and actual costs (AC) expended to produce the work of the project. Cost variance (CV), schedule variance (SV), cost performance index (CPI), and schedule performance index (SPI) are the formulas used with the EVM technique.
Define estimate to complete (ETC), estimate at completion (EAC), and budget at completion (BAC). Estimate to complete (ETC) is a forecast of the cost of all remaining project work and is usually provided by the project team members. Estimate at completion (EAC) is a projection of final project costs obtained by adding the ETC to the actual project costs to date. Budget at completion (BAC) is the total amount of the budget for the work package, control account, schedule activity, or project.
Define the purpose for the Managing Stakeholder Expectations process. Managing Stakeholder Expectations involves communicating, resolving issues, improving project performance by implementing change requests, and managing concerns.
Explain the purpose for the Distribute Information process. Distribute Information is concerned with getting stakeholders information about the project in a timely manner. This is accomplished using status reports, project meetings, review meetings, and so on, depending on their communication preferences.
Name the types of barriers a project manager might face when managing teams. Time zones, language and communication barriers, cultural differences, hierarchical barriers, and technology barriers are all types of barriers.
10.                    Closing the Project
Summary
Project closeout should be performed when the project ends, when a phase of a project ends, or when a project is killed or canceled. The Closing process group is the most often skipped on projects because project managers and team members are anxious to move on to their next assignments. It’s important to take the time to perform the steps in the Closing process group so that you can obtain sign-off on the project, turn over the product to the organization, release project resources, close out the contract, perform a post–project review, document lessons learned, and create a final project report.
Four types of project endings encompass the majority of reasons a project comes to an end. They are addition, starvation, integration, and extinction.
Close Procurements involves completing and settling the terms of the contract and documenting its acceptance. Product verification occurs here and that determines whether the work was completed accurately and satisfactorily.
Administrative Closure involves gathering and centralizing all the project documents, performing the post-project review, and writing the final project report.
The post-project review is conducted at the conclusion of the project, and its primary purpose is to collect and document lessons learned. Perhaps the most important element of project closure is the lessons learned document. This entails identifying where things went wrong, what things went well, and the alternatives you considered during the course of the project. Lessons learned are an extremely useful reference for future projects regarding what worked and what didn’t, for estimating techniques, for establishing templates, and more.
Post-mortem analysis is performed on projects that are canceled or end prematurely. This is much like the lessons learned process where information is gathered and recorded regarding what went wrong, the decisions for cancelation, and the plan for turning over completed deliverables.
The project close report is distributed to the stakeholders and includes several elements, including the project’s goal, the statement of acceptance, a summary of costs and schedule data, and lessons learned data.
Exam nuggets
Name the four reasons for project endings. They are addition, starvation, integration, and extinction.
Understand the steps involved in closing a project or phase. The steps include obtaining sign-off and acceptance, transferring the product to the organization, releasing project resources, closing out contracts, performing Administrative Closure, documenting historical information, conducting post-mortem analysis, and conducting post-project reviews.
Explain the purpose of obtaining formal customer or stakeholder sign-off. The formal sign-off documents that the customer accepts the project work and that the project meets the defined requirements. It also signals the official closure of the project and the transfer of the final product of the project to the organization.
Describe transferring the project results to the organization. Transferring the project results occurs once sign-off has been obtained. There should be a documented transition plan for transferring the project results, including describing the type of training or skills needed to maintain the product. License costs, warranty coverage and time period, user documentation, and any other materials needed by the organization should be included in the transfer.
Understand the key elements of the Close Procurements process. Contract closeout verifies that all the work described in the contract was completed satisfactorily per the contract terms and conditions. It includes notifying the vendor in writing that the work of the contract was accepted.
Name the procedures involved in Administrative Closure. Administrative Closure involves gathering and centralizing project documents, performing a post-project review, writing the final project close report, archiving project documents, and documenting lessons learned and historical information.
Describe lessons learned. Lessons learned describe the successes and failures of the project.

Good luck! You will need it.

Comments

  1. Stay focused on your core business operations through getting IT managed services London. Avoid getting distracted by IT problems and boost up your business productivity easily!
    Check out more at: https://www.thebesgroup.co.uk/

    ReplyDelete
    Replies
    1. It seems like you're referring to the reasons projects may end based on the text "The Dynamics of Software Development" by Jim McCarthy. Here's an explanation of each reason:

      Addition: Projects end because they have accomplished their objectives or fulfilled their scope. This could mean delivering a product, achieving a milestone, or completing the defined work.

      Starvation: Projects end due to lack of resources, funding, or support. When essential inputs like manpower, budget, or management attention are withdrawn or insufficient, the project cannot continue effectively.

      Integration: Projects may end because they are integrated into a larger effort or initiative. This could involve merging the project's outcomes or team into another project or organizational structure, thereby concluding its independent existence.

      Extinction: Projects end because they are no longer relevant or useful. This could be due to changes in market conditions, technology obsolescence, or shifts in organizational priorities, rendering the project unnecessary or obsolete.


      final year projects for computer science

      Final Year Project Centers in Chennai

      IEEE projects for cse

      Delete
  2. I wanted to thank you for this great blog! I really enjoying every little bit of it and I have you bookmarked to check out new stuff you post.
    Project Management

    ReplyDelete
  3. Your site is actually awe-inspiring. I've discovered numerous brand new points. The right path associated with setting up can also be intriguing. You've chosen really amazing subject. We valued this.
    Consultation manager

    ReplyDelete
  4. Iam very happy after find this post and really thank you. Thanks for sharing this Informative content. Well explained. Got to learn new things from your Blog. I wanted to write a little comment to support you and wish you a good continuation. All the best for all your blogging efforts. To make a project successful project management tools plays an important role. Using Project Management tools is essential and increases the chances of successfully completing the project on time and within the budget, irrespective of the size of the project.
    Top Agile Project Management Tools

    ReplyDelete
  5. Thank you for this very good and informative post.

    ReplyDelete
    Replies
    1. This comment has been removed by the author.

      Delete
    2. This comment has been removed by the author.

      Delete
    3. This comment has been removed by the author.

      Delete
    4. This comment has been removed by the author.

      Delete
  6. This is extremely fascinating substance! I have completely delighted in perusing your focuses and have reached the conclusion that you are right about a hefty portion of them. You are extraordinary.
    Benefits of Enterprise Content Management

    ReplyDelete
  7. Let me share all of you about #10 Tips for Project Management Success, I hope you enjoy it

    1. Plan your day using time management techniques

    As a project manager, time management skills are essential because you are dealing with a wide range of tasks that demand a quick turnaround time. Planning your day will go a long way in keeping you organized and increasing your productivity. Assist your task planning by using project management software which helps you track the work of you and your team.

    If you are not very tech savvy, a simple to-do list can also be a great organizational tool. Prioritize your most important tasks by putting them at the top of the list and less important ones at the bottom. Having a visual plan of your daily tasks helps to keep you on track and aware of time.

    Related post: Free ebook 104 secrets to become a great project manager

    2. Include stakeholders in important project conversations

    While you will have plenty of responsibilities regarding the project, don’t neglect your clients.

    Good communication is essential is keeping both parties informed of project progression, curtailing scope creep, and apprised of changing requirements. Some clients may have different expectations when it comes to communication, so make sure to establish the frequency and type of communication (like emails, phone calls, and face-to-face conversations) at the beginning of your project.

    Establishing communication expectations early helps alleviate stakeholder uncertainty about communication frequency and delivery.

    3. Regularly communicate with your team

    Daily team communication helps keep misunderstandings and unclear requirements under control. Keeping your team informed in every step of the project is essential to project management success.

    For example, a study published by Procedia Technology found that good communication skills were the cornerstone of project management. The study examined over 300 “construction project managers, architects, construction managers, engineers and quantity surveyors” and their successes and failures on various construction projects.

    4. Anticipate project setbacks

    Even the best-laid plans often go awry.

    Remember that even with a high amount of planning and attention to detail, your project may still encounter some challenges. Pay attention to complaints from stakeholders or colleagues, and other warning signs, like a missed deadline or cost overrun, that there may be a problem.

    Preventing a crisis will keep your project running smoothly, save you a lot of time, and keep you, your team, and your stakeholders confident in progressing with the project.

    Unfortunately not every complication can be avoided. Crisis management skills are essential for dealing with the unexpected. Project managers need to be flexible and pragmatic. Improvise and make sharp decisions when needed.

    Related post: 92 free project management templates

    5. Stay focused on the details

    A common problem project managers encounter is having the project aims not aligned with the organization’s objectives. A great project manager will strategize a plan for the project to lead back to the overall success of the business.

    Know your project’s scope by heart and avoid wandering outside of the project’s requirements. It’s too easy to get lost in minor details and forget what your focus is, so a well-planned project scope is essential for success.

    And final, you should use KPI to measure effectiveness of the project, here are full list: 76 project management KPIs

    ReplyDelete
  8. Adetoal Abiodun.O3 September 2018 at 10:46

    Thank you Sir for this summary.

    ReplyDelete
  9. Thanks for the best summary towards CompTIA or PMP project management examinations

    GREAT WORK
    IMPRESSIVE!!!
    REALLY APPRECIATE YOUR WORK!!!
    Project Management India

    ReplyDelete
  10. Extraordinary post! I am really preparing to over this data, It's exceptionally useful for this blog.Also incredible with the majority of the significant data you have Keep up the great work you are progressing admirably. I am also writing blogs on project management
    & PMP certification.

    ReplyDelete
  11. This comment has been removed by the author.

    ReplyDelete
  12. Nice and very informative post regarding project management service..

    Thanks for sharing..

    project management service



    ReplyDelete
  13. i love this wedding theme as well a couple and i want to share the also great one Best Event Planners in Pakistan they help to make our event best.

    ReplyDelete
  14. Nice and very informative post..

    Thanks for sharing..

    Construction project management


    ReplyDelete
  15. Agree with the information... Project Management System Software is the application of tools and techniques to organize the project activities to successfully meet the project goals.

    ReplyDelete
  16. Yes its good tool and nice article. but for implementation need the Project management
    Project management knowledge provided by PMI.

    ReplyDelete
  17. Project management is the application of processes, methods, skills, knowledge and experience to achieve specific project objectives according to the project acceptance criteria within agreed management parameters. Project management has final deliverable that are constrained to a finite timescale and budget.

    ReplyDelete
  18. Project Management System Software is the best ERP software that makes and manages all the task digitally and helps you in bringing advancement at every level.

    ReplyDelete
  19. It is my great pleasure to visit your website and to enjoy your excellent "project management" post here. I like them very much. I can feel that you paid much attention to those articles, as all of them make sense and are very useful. Thanks so much for sharing.


    Business Consultants in Canada, ERP Solution, Budgeting and Monitoring

    ReplyDelete
  20. You have explained about project management's need and process very effectively. Thanks for sharing !!!! Fahim Moledina is the founder of OptiSyn Consulting which provides- Change, Project Management and Transformation services.

    ReplyDelete
  21. Thanks for sharing this blog. Fahim Moledina helps us to make project management strategy for creating new business.

    ReplyDelete
  22. Great flow in writing. To be versatile in your project management, learn Prince2 foundation

    ReplyDelete
  23. SSbizconsulting is an established firm of experienced and qualified consultants providing business & IT consulting services in Sydney, Australia. We provide project management services and IT consulting services to small and large companies across Sydney. To find out more about our services, please contact us.

    ReplyDelete
  24. thanks for this blog its very informative for me because i also have a similar content of construction project management in Pakistan

    ReplyDelete


  25. Such an informative post. Thank you for sharing
    Project Online EPM Implementation

    ReplyDelete
  26. I recommend Team Pro4People :)

    If you need help ISO13485 - more information here https://pro4people.com/iso-13485-medical-devices-certified-quality-management-system/

    Nice blog !!!

    ReplyDelete
  27. This topic has always been one of my favorite subjects to read about Project management services. I have found your post to be very rousing and full of good information . Thank you for providing useful information

    ReplyDelete
  28. Thank you for being supportive by sharing your own thoughts and ideas with us. Please keep sharing such information.
    Construction accounting services in London

    ReplyDelete

  29. Searching and reading about the faility management services is my favourite topic. Thank you for providing full of informative blog. I would love to read more on this topic.

    ReplyDelete
  30. I am learning pmp, this is very good information to learn more about other topics also. i am waiting for more articles by the same author thank you for valuable information pmp certification

    ReplyDelete
  31. It is my great pleasure to visit your website and to enjoy your excellent post here. I like them very much. I can feel that you paid much attention to those articles, as all of them make sense and are very useful. Thanks so much for sharing.
    Accounting and Bookkeeping services Mississauga

    ReplyDelete
  32. Learn how to control cost in project management and how to do a construction take off with our self paced courses.

    ReplyDelete
  33. Providing the best project management services to customers is a challenge now. After reading your article all the confusion has gone. These points you have shared in your blog are very beneficial for the project manager. I've learned from your guide, it's very simple but effective writing. Thank you.

    ReplyDelete
  34. It is my great pleasure to visit your website and to enjoy your excellent post here. I like them very much. I can feel that you paid much attention to those articles, as all of them make sense and are very useful. Thanks so much for sharing.
    Business consultants in Canada

    ReplyDelete
  35. Your blog is really good and informative. These Online Project Management tools are easy to handle and easy to track the data.

    ReplyDelete
  36. You truly did more than visitors’ expectations. Thank you for rendering these helpful, trusted, edifying and also cool thoughts on the topic.
    Procurement Management Software
    Purchase Management Software
    e Procurement Management Software
    Procurement Tracking Software

    ReplyDelete
  37. You've made some good points there.I was able to find good information from your blog articles, it's very useful Information about this topic "Time Tracking Software "

    ReplyDelete
  38. I am curious to find out what blog system you're utilizing? I'm experiencing some minor security issues with my latest website and I would like to find something more secure. Do you have any recommendations?
    workplace governance systems Perth

    ReplyDelete
  39. M3M Golf Estate Providing Ready to Move Golf Facing Apartments in Gurgaon for sale with Eco-friendly Landscapes Equipped With High-End Luxury & Furnishing. Book Now!

    ReplyDelete
  40. DLF The Ultima Gurgaon is Ready To Move project. DLF Builders offers Residential Properties in DLF The Ultima. Snap for Project Price List, Map, Photos, Videos, Reviews, Location Highlights & Nearby comparative projects on dlftheultimas.in.

    ReplyDelete
  41. Very informative post! This post gives truly quality information. I find that this post is really amazing. Thank you for this brief explanation and very nice information.
    AOL Mail Inbox

    ReplyDelete
  42. I was curious if you ever thought of changing the layout of your site? Its very well written; I love what youve got to say. But maybe you could a little more in the way of content so people could connect with it better. Youve got an awful lot of text for only having 1 or 2 images. Maybe you could space it out better?
    workplace governance systems Perth

    ReplyDelete
  43. Thanks for providing these kinds of Information about Time Tracking software. This post is very useful for me I bookmark this and I hope your next article coming soon

    Visit here :- Time Tracking Tool

    ReplyDelete
  44. You have provided informative details.
    ERP Gold| https://www.erp.gold/

    ReplyDelete
  45. Nice blog! Your blog unique and very informative for everyone. If you are looking for quality training courses then knowledgekafe is best for you. Here you enroll and attend training courses like project management course, MS office online course , Arabic speaking classes Social media marketing courses and so on.

    ReplyDelete
  46. Brilliant put up your article is admirable and full of detail. I was really impressed with your interesting blog and the plenty in the content. Thanks for sharing.

    Visit here :- Project Tracking Software

    ReplyDelete
  47. Really nice and informative..I found this blog very useful. Quantity surveyors in UAE

    ReplyDelete
  48. Thanks for sharing this post. We deliver, manage the complete process which includes the discipline of project planning, project monitoring, managing resources & subcontractors and supporting design deliverables. we are one the best Project management Consultants in UAE. for more information you can contact +971 6 557 3924. Project management Consulting Services

    ReplyDelete
  49. Wow what a great post.It provides a brief information about Project Management Consultants. But if you are looking for the Services in UAE . Visit us at yellowpages.ae

    ReplyDelete
  50. I am really lucky that I found your website by mistake, really useful information about Project Management. Thanks for this informative information and I bookmarked it.

    Visit: Time Tracking Software

    ReplyDelete
  51. TC Consultancy specializes in customizing its approach for diverse construction projects as per the needs and challenges of each project, irrespective of its size and scope. We specialize, best in Quantity Surveying Services .Project Management, Project Development, Tenancy and Facility Support Management. for more information you can contact +971 6 557 3924

    ReplyDelete
  52. We deliver, manage the complete process which includes the discipline of project planning, project monitoring, managing resources & subcontractors and supporting design deliverables. we are one the best Project management Consultants in UAEProject management Consulting Services .for more information you can contact +971 6 557 3924.

    ReplyDelete
  53. The development has a vital role in any part of the world, especially in the United Arab Emirates. The infrastructure of a country uncovers the budgetary wealth and the living status of individuals. There are various kinds of construction companies in Dubai such as concrete structures, Steel outline structures, Light gauge steel, wood-framed development, load-bearing construction, solid development, pre-designed structures, mechanical structure, and 3d printed building.
    construction companies in Dubai list

    ReplyDelete
  54. The development has a vital role in any part of the world, especially in the United Arab Emirates. The infrastructure of a country uncovers the budgetary wealth and the living status of individuals. There are various kinds of construction companies in Dubai such as concrete structures, Steel outline structures, Light gauge steel, wood-framed development, load-bearing construction, solid development, pre-designed structures, mechanical structure, and 3d printed building.
    All Construction Companies in UAE

    ReplyDelete
  55. We deliver, manage the complete process which includes the discipline of project planning, project monitoring, managing resources & subcontractors and supporting design deliverables. we are one the best Project management Consultants in UAEProject management Consulting Services in Saudi arabia .for more information you can contact +971 6 557 3924.

    ReplyDelete
  56. TC Consultancy has extensive experience of providing a total Project development for all types Services of building, transportation, power, defence etc. for more information you can contact +971 6 557 3924
    Project Development Sharjah

    ReplyDelete
  57. I have read your article, it is very informative and helpful for me.I admire the valuable information you offer in your articles. Thanks for posting it.. https://westasianetwork.com/ashford-formula-united-arab-emirates.php

    ReplyDelete
  58. Thanks for sharing this great content. It is really informative and useful. You can also check this Similar site for PMP course.

    ReplyDelete
  59. I was searching for a proper explanation anti money laundering certification free. Thanks, admin, for sharing such wonderful content on this topic. Now I have got everything I need about it. Here’s another informative content on. Anti Money Laundering Certification Free You will get well researched information about it.

    ReplyDelete
  60. Nice Content.
    An advise to all who are planning to obtain a PMP Certification. As much as possible, enroll your self with ATP. Enjoy the benefits from Premium PMI Authorized Training Partner. By choosing an unapproved training provider, you might waste your time, resources, and money. For example, many unapproved institutes’ training material is a copy and paste of the PMBOK(r) Guide. However, the PMP 2021 exam is completely different with 50% of the exam questions focusing on Agile practice and 3 domains (People, Process, and Business Environment). Should you need Free Consultation for PMP or any certification like ASQ-CMQ /OE, please contact me : Mobile: +971.56.9012099 Email ID: Alegria@3foldtraining.com

    ReplyDelete
  61. This comment has been removed by the author.

    ReplyDelete
  62. Nice post, thanks for sharing...!!


    Want to know about PMP Certification Training ? MindCypress is here at your service. Project Management is a vast subject that helps in the growth process of a company. We ensure to serve you with ample amount of knowledge and assist you in using your skills wisely.

    ReplyDelete
  63. Nice blog thanks for sharing
    #FIDIC CERTIFICATION

    ReplyDelete
  64. Thanks for sharing such a nice post with lot of content..FIDIC

    ReplyDelete
  65. This blog is very informative thanks for sharing and keep on posting .#ISO CERTIFICATION
    #lead auditor course

    ReplyDelete
  66. The information you have provided about Time Tracking Software is excellent, and I have gained a lot of knowledge. Hopefully, you will continue to share interesting content about this topic.

    Visit: Time Tracking Software

    ReplyDelete
  67. Great Article, Thanks for sharing with us. For Agile Management Software Visit my website: Agile Management Software

    ReplyDelete
  68. Thank you for providing such great insights in this article, it was very helpful.
    for more information regarding Project management certification courses please get in touch with 360DigiTMG team.
    PMP Certification course

    ReplyDelete
  69. I have visited many websites but this is the best so far. I have learned a lot from this post which will help me a lot in future. Plan Management

    ReplyDelete
  70. Fantastic Article!! I came on your blog and discovered a wealth of knowledge regarding project management software products. Thank you for sharing this data. I'm hoping you'll keep sharing interesting article on this subject.

    ReplyDelete
  71. Thanks for sharing this informative bog about project management I find this very useful for my study as well which isPGDM in operations Keep sharing.

    ReplyDelete
  72. Nice blog! Thanks for sharing PMP Training

    ReplyDelete
  73. shwetal chaudhari1 December 2021 at 21:21

    Thanks for explaining CompTIA or PMP project management examination process in a very easy manner. Upskill yourself in Project Management by exploring Prince2 Certification, prince2 agile certification courses.

    ReplyDelete
  74. Thanks for sharing the post with us
    dassm

    ReplyDelete
  75. TC Consultancy, as an established project management service provider in Dubai, Sharjah,, Kuwait, Qatar, Bahrain, Oman, KSA. Project management Consulting Services, project monitoring, managing resources & subcontractors and supporting design deliverables to bring about the successful completion of specific project goals and objectives.

    ReplyDelete
  76. Thanks for this post...BBL Foods provides Project Management Consulting for Innovative food machinery and Food manufacturing machinery besides required engineering services and support for food projects in any volume.
    5 roll refiner machinery
    Biscuit Machine manufacturer
    Potato chips line supplier

    ReplyDelete

  77. project management

    Project Management is a vital element that chooses the achievement or disappointment of a task. visit our blog to know more-PROJECT MANAGEMENT

    ReplyDelete
  78. PMP ONLINE COURSE

    PMP Online Training Benefits For Obtaining Your PMP visit our blog to know more-PMP ONLINE COURSE

    ReplyDelete

  79. PMP CERTIFICATION COURSE


    The PMP course provides managers with the latest information on Project Management norms and practices.Click here to know more PMP CERTIFICATION

    ReplyDelete
  80. Hey, If you want to know some - requirement for pmp certification Then you should check this out

    ReplyDelete
  81. wonderful Post.
    https://www.knowlathon.com/blog/how-to-do-pmp-certification/

    ReplyDelete
  82. This information you have supplied is incredibly useful. It's great that this since it helps us and increases our knowledge. I'm grateful you shared this article. asset inventory management software

    ReplyDelete
  83. I was searching about the pmp training in karachi for a long time. Your blog has the valueable information about the topic. I've learned many good points from your blog. Thank you and keep writing.

    ReplyDelete
  84. This comment has been removed by the author.

    ReplyDelete
  85. Thanks for sharing a valuable information & love to hear from you soon!

    Construction document management software

    ReplyDelete
  86. Hey, nice blog, I found many things that are very informative.

    Biobanks | biorepositories
    human-samples | patient-samples

    ReplyDelete
  87. Bhurban Meadows prioritizes sustainability, making it a future-ready investment with a focus on eco-friendly practices.
    Luxury Cottages in Bhurban

    ReplyDelete
  88. Empro group Does handle project management as its core service.

    ReplyDelete

Post a Comment

Popular posts from this blog

WHEN MONEY FAILS… Part 3

The Leader in You!

WHEN MONEY FAILS...Part 2